Showcase — Completed Works
Rollup last refreshed: 2026-09-01 08:48:19.512575
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Constr of Cement Concrete Roads
9 works
₹80.91 L sanctioned
₹17.67 L spent (22%)
02
Construction of Road and Culvert
10 works
₹79.65 L sanctioned
₹57.34 L spent (72%)
03
Construction of Check Dam/Stop Dam
16 works
₹46.91 L sanctioned
₹30.65 L spent (65%)
04
Construction of Trench
14 works
₹45.40 L sanctioned
₹38.00 L spent (84%)
05
Farm Pond
14 works
₹30.89 L sanctioned
₹27.74 L spent (90%)
06
Plantation
11 works
₹23.22 L sanctioned
₹10.76 L spent (46%)
07
Rural Housing
112 works
₹21.54 L sanctioned
₹20.45 L spent (95%)
08
Terracing
9 works
₹16.62 L sanctioned
₹12.58 L spent (76%)
09
Construction of Well
4 works
₹9.02 L sanctioned
₹4.09 L spent (45%)
10
Construction of Percolation Tank
5 works
₹8.30 L sanctioned
₹5.60 L spent (67%)