Scope
Works completed
200
Sanctioned (pure scheme)
₹3.21 Cr
Expenditure since inception
₹2.65 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Solid and Liquid Waste Management
26 works
₹1.54 Cr sanctioned
₹1.50 Cr spent (97%)
02
Construction of Road and Culvert
17 works
₹34.65 L sanctioned
₹25.13 L spent (73%)
03
Constr of Cement Concrete Roads
24 works
₹16.93 L sanctioned
₹8.97 L spent (53%)
04
Terracing
3 works
₹16.42 L sanctioned
₹14.74 L spent (90%)
05
Plantation
6 works
₹15.85 L sanctioned
₹5.05 L spent (32%)
06
Construction of Check Dam/Stop Dam
3 works
₹11.54 L sanctioned
₹9.62 L spent (83%)
07
Repair & maint of Water Harvesting Structures
2 works
₹9.60 L sanctioned
₹8.28 L spent (86%)
08
Boulder Check/Gully Plug
5 works
₹8.39 L sanctioned
₹4.78 L spent (57%)
09
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
2 works
₹8.18 L sanctioned
₹6.66 L spent (81%)
10
Construction of Bund
3 works
₹7.50 L sanctioned
₹5.69 L spent (76%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Construction of Toilets 35 0.04 0.04
100%
2 Construction of NADEP/Vermi Compost Pit 31 0.05 0.05
97%
3 Rural Housing 30 0.05 0.05
92%
4 Solid and Liquid Waste Management 26 1.54 1.50
98%
5 Constr of Cement Concrete Roads 24 0.17 0.09
53%
6 Construction of Road and Culvert 17 0.35 0.25
73%
7 Plantation 6 0.16 0.05
32%
8 Boulder Check/Gully Plug 5 0.08 0.05
57%
9 Construction of Tank 4 0.01 0.00
63%
10 Land Development 4 0.05 0.03
57%
11 Terracing 3 0.16 0.15
90%
12 Construction of Check Dam/Stop Dam 3 0.12 0.10
83%
13 Construction of Bund 3 0.07 0.06
76%
14 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 2 0.08 0.07
82%
15 Repair & maint of Water Harvesting Structures 2 0.10 0.08
86%
16 Construction of Crematorium 1 0.05 0.02
36%
17 Construction of Play field 1 0.04 0.01
40%
18 Constr of Compound wall 1 0.00 0.00
58%
19 Repair & maint of Percolation Tank 1 0.05 0.03
61%
20 Well Recharge 1 0.04 0.03
74%
Total 200 3.21 2.65
All 20 rows (zero-value rows hidden) ⇩ Export to Excel