| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Construction of Toilets | 112 | 6.69 | 6.71 | 100% |
| 2 | Rural Housing | 105 | 17.44 | 17.14 | 98% |
| 3 | Cattle Shed | 18 | 8.32 | 6.83 | 82% |
| 4 | Constr of Cement Concrete Roads | 18 | 14.40 | 10.05 | 70% |
| 5 | Construction of Road and Culvert | 17 | 63.40 | 46.94 | 74% |
| 6 | Solid and Liquid Waste Management | 12 | 41.70 | 38.75 | 93% |
| 7 | Construction of NADEP/Vermi Compost Pit | 9 | 2.27 | 2.23 | 98% |
| 8 | Construction of Check Dam/Stop Dam | 6 | 24.87 | 16.79 | 68% |
| 9 | Goat Shelter | 5 | 2.00 | 0.07 | 4% |
| 10 | Well Recharge | 5 | 1.29 | 1.22 | 94% |
| 11 | Plantation | 5 | 14.20 | 2.98 | 21% |
| 12 | Land Development | 4 | 0.46 | 0.03 | 8% |
| 13 | Construction of Trench | 3 | 9.99 | 8.87 | 89% |
| 14 | Constr of Compound wall | 3 | 16.73 | 14.84 | 89% |
| 15 | Repair & maint of Pond/ Tank | 3 | 6.27 | 4.82 | 77% |
| 16 | Construction of Crematorium | 2 | 8.58 | 8.14 | 95% |
| 17 | Constr of Aganwadi | 2 | 0.38 | 0.31 | 82% |
| 18 | Construction of Tank | 2 | 0.48 | 0.28 | 59% |
| 19 | Construction of Play field | 2 | 3.72 | 3.25 | 87% |
| 20 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 1 | 1.58 | 1.58 | 100% |
| 21 | Farm Pond | 1 | 1.48 | 1.23 | 83% |
| Total | 335 | 246.24 | 193.07 |