| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 460 | 0.84 | 0.81 | 96% |
| 2 | Construction of Check Dam/Stop Dam | 17 | 0.71 | 0.60 | 85% |
| 3 | Land Development | 14 | 19.63 | 0.05 | 0% |
| 4 | Constr of Cement Concrete Roads | 13 | 0.18 | 0.17 | 95% |
| 5 | Construction of Road and Culvert | 12 | 0.41 | 0.28 | 70% |
| 6 | Well Recharge | 10 | 0.05 | 0.04 | 78% |
| 7 | Plantation | 5 | 0.06 | 0.02 | 32% |
| 8 | Farm Pond | 4 | 0.01 | 0.01 | 71% |
| 9 | Construction of Crematorium | 3 | 0.12 | 0.08 | 69% |
| 10 | Constr of Gabion | 3 | 0.03 | 0.02 | 51% |
| 11 | Construction of Well | 3 | 0.07 | 0.06 | 86% |
| 12 | Construction of Percolation Tank | 2 | 0.10 | 0.09 | 96% |
| 13 | Construction of Trench | 2 | 0.19 | 0.19 | 99% |
| 14 | Culvert | 2 | 0.01 | 0.01 | 91% |
| 15 | Community Sanitary Complex | 1 | 0.00 | 0.00 | 87% |
| 16 | Constr of Aganwadi | 1 | 0.03 | 0.03 | 100% |
| 17 | Constr of GP Bhawan | 1 | 0.13 | 0.10 | 78% |
| 18 | Construction of Bund | 1 | 0.05 | 0.05 | 99% |
| 19 | Repair & Maint of Check Dam/Stop Dam | 1 | 0.15 | 0.14 | 96% |
| 20 | Repair & maint of Pond/ Tank | 1 | 0.09 | 0.09 | 99% |
| 21 | Solid and Liquid Waste Management | 1 | 0.02 | 0.01 | 61% |
| Total | 557 | 22.87 | 2.84 |