Scope
Works completed
238
Sanctioned (pure scheme)
₹4.04 Cr
Expenditure since inception
₹2.82 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
20 works
₹65.54 L sanctioned
₹62.13 L spent (95%)
02
Construction of Check Dam/Stop Dam
30 works
₹57.07 L sanctioned
₹43.90 L spent (77%)
03
Construction of Road and Culvert
6 works
₹48.98 L sanctioned
₹13.71 L spent (28%)
04
Plantation
13 works
₹39.92 L sanctioned
₹16.93 L spent (42%)
05
Cattle Shed
1 works
₹37.85 L sanctioned
₹37.70 L spent (100%)
06
Constr of Cement Concrete Roads
24 works
₹32.77 L sanctioned
₹19.50 L spent (60%)
07
Construction of Tank
4 works
₹24.80 L sanctioned
₹16.58 L spent (67%)
08
Construction of Bund
7 works
₹16.77 L sanctioned
₹13.44 L spent (80%)
09
Farm Pond
8 works
₹16.62 L sanctioned
₹12.66 L spent (76%)
10
Constr of Gabion
5 works
₹14.67 L sanctioned
₹14.28 L spent (97%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 47 9.28 8.83
95%
2 Construction of Check Dam/Stop Dam 30 57.07 43.90
77%
3 Construction of NADEP/Vermi Compost Pit 29 2.05 1.58
77%
4 Constr of Cement Concrete Roads 24 32.77 19.50
60%
5 Construction of Well 20 65.54 62.13
95%
6 Plantation 13 39.92 16.93
42%
7 Well Recharge 11 4.89 1.86
38%
8 Construction of Toilets 9 1.08 1.08
100%
9 Farm Pond 8 16.62 12.66
76%
10 Land Development 8 12.45 4.26
34%
11 Construction of Bund 7 16.77 13.44
80%
12 Construction of Road and Culvert 6 48.98 13.71
28%
13 Constr of Gabion 5 14.67 14.28
97%
14 Construction of Tank 4 24.80 16.58
67%
15 Culvert 4 3.89 3.70
95%
16 Construction of Trench 3 6.18 3.92
64%
17 Constr of Compound wall 3 0.19 0.19
97%
18 Community Sanitary Complex 2 0.88 0.78
89%
19 Renovation of traditional water bodies 2 5.50 2.86
52%
20 Cattle Shed 1 37.85 37.70
100%
21 Construction of Recharge Pits 1 0.15 0.15
99%
22 Construction of Crematorium 1 2.45 2.24
91%
Total 238 403.96 282.27
All 22 rows (zero-value rows hidden) ⇩ Export to Excel