MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-09-01 08:48:19.512575
to
to
Reset filters
Scope
Works completed
189
Sanctioned (pure scheme)
₹3.43 Cr
Expenditure since inception
₹2.42 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
17 works
₹96.84 L sanctioned
₹71.53 L spent (74%)
02
Construction of Road and Culvert
6 works
₹46.49 L sanctioned
₹10.56 L spent (23%)
03
Cattle Shed
3 works
₹39.92 L sanctioned
₹36.81 L spent (92%)
04
Construction of Well
11 works
₹33.42 L sanctioned
₹27.59 L spent (83%)
05
Constr of Cement Concrete Roads
14 works
₹17.64 L sanctioned
₹17.57 L spent (100%)
06
Construction of Tank
1 works
₹16.80 L sanctioned
₹16.79 L spent (100%)
07
Constr of GP Bhawan
1 works
₹14.23 L sanctioned
₹2.78 L spent (20%)
08
Rural Housing
77 works
₹14.07 L sanctioned
₹13.56 L spent (96%)
09
Land Development
11 works
₹13.32 L sanctioned
₹7.78 L spent (58%)
10
Construction of Percolation Tank
3 works
₹11.40 L sanctioned
₹8.63 L spent (76%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 77 14.07 13.56
96%
2 Construction of Check Dam/Stop Dam 17 96.84 71.53
74%
3 Constr of Cement Concrete Roads 14 17.64 17.57
100%
4 Farm Pond 11 0.76 0.51
67%
5 Construction of Well 11 33.42 27.59
83%
6 Land Development 11 13.32 7.78
58%
7 Construction of Road and Culvert 6 46.49 10.56
23%
8 Solid and Liquid Waste Management 6 0.60 0.59
98%
9 Plantation 5 11.27 6.40
57%
10 Well Recharge 4 0.24 0.09
38%
11 Construction of Crematorium 4 10.38 10.05
97%
12 Construction of NADEP/Vermi Compost Pit 3 1.20 1.08
90%
13 Construction of Trench 3 7.43 6.03
81%
14 Construction of Percolation Tank 3 11.40 8.63
76%
15 Cattle Shed 3 39.92 36.81
92%
16 Community Sanitary Complex 2 1.40 1.19
85%
17 Repaire and Maint of NADEP/Vermi Compost Pit 2 0.99 0.93
94%
18 Constr of GP Bhawan 1 14.23 2.78
20%
19 Constr of Gabion 1 0.45 0.44
98%
20 Construction of Recharge Pits 1 0.24 0.00
1%
21 Constr of Compound wall 1 1.54 0.62
40%
22 Repair & maint of Pond/ Tank 1 1.30 0.02
1%
23 Construction of Tank 1 16.80 16.79
100%
24 Construction of Toilets 1 0.83 0.82
99%
Total 189 342.76 242.38
All 24 rows (zero-value rows hidden) ⇩ Export to Excel