Showcase — Completed Works

Rollup last refreshed: 2026-09-01 08:48:19.512575
to
to
Reset filters
Scope
Works completed
816
Sanctioned (pure scheme)
₹3.98 Cr
Expenditure since inception
₹3.45 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
505 works
₹89.69 L sanctioned
₹87.74 L spent (98%)
02
Construction of Well
22 works
₹48.97 L sanctioned
₹43.67 L spent (89%)
03
Construction of Check Dam/Stop Dam
8 works
₹31.45 L sanctioned
₹35.88 L spent (114%)
04
Constr of Cement Concrete Roads
35 works
₹30.89 L sanctioned
₹25.34 L spent (82%)
05
Solid and Liquid Waste Management
99 works
₹22.89 L sanctioned
₹21.75 L spent (95%)
06
Construction of Road and Culvert
12 works
₹21.34 L sanctioned
₹20.62 L spent (97%)
07
Construction of Trench
2 works
₹19.67 L sanctioned
₹13.06 L spent (66%)
08
Construction of Canal
2 works
₹19.54 L sanctioned
₹17.80 L spent (91%)
09
Constr of Compound wall
2 works
₹19.43 L sanctioned
₹12.62 L spent (65%)
10
Constr of GP Bhawan
2 works
₹15.47 L sanctioned
₹11.20 L spent (72%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 505 89.69 87.74
98%
2 Solid and Liquid Waste Management 99 22.89 21.75
95%
3 Construction of Toilets 87 10.37 10.26
99%
4 Constr of Cement Concrete Roads 35 30.89 25.34
82%
5 Construction of Well 22 48.97 43.67
89%
6 Construction of Road and Culvert 12 21.34 20.62
97%
7 Construction of Check Dam/Stop Dam 8 31.45 35.88
114%
8 Well Recharge 5 0.33 0.29
89%
9 Plantation 3 6.70 0.71
11%
10 Cattle Shed 3 2.34 2.16
93%
11 Construction of NADEP/Vermi Compost Pit 3 2.86 0.44
15%
12 Construction of Percolation Tank 3 9.19 5.04
55%
13 Construction of Bund 3 1.36 0.59
44%
14 Construction of Tank 3 6.88 6.33
92%
15 Constr of Aganwadi 2 2.79 2.10
76%
16 Constr of GP Bhawan 2 15.47 11.20
72%
17 Farm Pond 2 6.44 6.31
98%
18 Construction of Recharge Pits 2 7.18 3.41
48%
19 Land Development 2 9.91 6.50
66%
20 Repair & maint of Percolation Tank 2 7.13 6.56
92%
21 Constr of Compound wall 2 19.43 12.62
65%
22 Construction of Trench 2 19.67 13.06
66%
23 Construction of Canal 2 19.54 17.80
91%
24 Repair & maint of Water Harvesting Structures 2 0.50 0.21
43%
25 Community Sanitary Complex 2 0.88 0.87
99%
26 Construction of Fish Drying Infrastructure 1 0.93 0.88
95%
27 Construction of Crematorium 1 2.45 2.44
100%
28 Strengthening of Embankment 1 0.00 0.17
0%
Total 816 397.56 344.95