| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 147 | 24.17 | 23.40 | 97% |
| 2 | Construction of Bund | 23 | 5.21 | 4.95 | 95% |
| 3 | Construction of Recharge Pits | 17 | 2.90 | 2.40 | 83% |
| 4 | Farm Pond | 16 | 9.09 | 8.30 | 91% |
| 5 | Construction of Check Dam/Stop Dam | 12 | 40.99 | 39.66 | 97% |
| 6 | Constr of Cement Concrete Roads | 12 | 32.84 | 24.90 | 76% |
| 7 | Land Development | 11 | 6.06 | 5.24 | 87% |
| 8 | Terracing | 10 | 10.39 | 9.32 | 90% |
| 9 | Construction of Well | 8 | 14.64 | 11.34 | 77% |
| 10 | Plantation | 8 | 11.70 | 4.34 | 37% |
| 11 | Goat Shelter | 7 | 3.64 | 1.61 | 44% |
| 12 | Cattle Shed | 7 | 3.43 | 2.64 | 77% |
| 13 | Construction of Road and Culvert | 7 | 42.87 | 24.85 | 58% |
| 14 | Construction of Play field | 4 | 14.29 | 14.20 | 99% |
| 15 | Constr of Aganwadi | 4 | 9.45 | 9.39 | 99% |
| 16 | Construction of Trench | 2 | 8.20 | 8.18 | 100% |
| 17 | Constr of GP Bhawan | 2 | 1.30 | 1.29 | 99% |
| 18 | Boulder Check/Gully Plug | 1 | 1.25 | 0.20 | 16% |
| 19 | Construction of Crematorium | 1 | 3.53 | 3.50 | 99% |
| 20 | Repair & maint of Pond/ Tank | 1 | 2.99 | 3.03 | 101% |
| Total | 300 | 248.96 | 202.74 |