MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
2,81,707
Sanctioned (pure scheme)
₹4,561.17 Cr
Expenditure since inception
₹3,019.76 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
14,325 works
₹1,415.85 Cr sanctioned
₹610.95 Cr spent (43%)
02
Construction of Road and Culvert
10,092 works
₹616.24 Cr sanctioned
₹465.97 Cr spent (76%)
03
Plantation
11,387 works
₹339.47 Cr sanctioned
₹130.85 Cr spent (39%)
04
Construction of Trench
8,642 works
₹310.24 Cr sanctioned
₹251.47 Cr spent (81%)
05
Construction of Well
21,123 works
₹298.20 Cr sanctioned
₹234.12 Cr spent (79%)
06
Construction of Percolation Tank
4,196 works
₹294.05 Cr sanctioned
₹259.65 Cr spent (88%)
07
Rural Housing
1,56,720 works
₹292.06 Cr sanctioned
₹262.54 Cr spent (90%)
08
Construction of Bund
7,192 works
₹125.55 Cr sanctioned
₹107.97 Cr spent (86%)
09
Constr of Cement Concrete Roads
5,247 works
₹104.75 Cr sanctioned
₹84.92 Cr spent (81%)
10
Farm Pond
9,267 works
₹93.81 Cr sanctioned
₹70.70 Cr spent (75%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 1,56,720 292.06 262.54
90%
2 Construction of Well 21,123 298.20 234.12
79%
3 Construction of Check Dam/Stop Dam 14,325 1,415.85 610.95
43%
4 Plantation 11,387 339.47 130.85
39%
5 Construction of Road and Culvert 10,092 616.24 465.97
76%
6 Farm Pond 9,267 93.81 70.70
75%
7 Construction of Trench 8,642 310.24 251.47
81%
8 Land Development 7,346 83.23 56.65
68%
9 Construction of Bund 7,192 125.55 107.97
86%
10 Constr of Cement Concrete Roads 5,247 104.75 84.92
81%
11 Construction of Percolation Tank 4,196 294.05 259.65
88%
12 Boulder Check/Gully Plug 2,660 27.24 20.86
77%
13 Well Recharge 2,477 36.31 27.28
75%
14 Construction of Toilets 2,452 15.68 9.78
62%
15 Solid and Liquid Waste Management 1,930 17.76 13.82
78%
16 Construction of Recharge Pits 1,663 16.77 13.24
79%
17 Construction of NADEP/Vermi Compost Pit 1,552 7.12 3.86
54%
18 Renovation of traditional water bodies 1,518 45.52 39.47
87%
19 Construction of Tank 1,270 74.58 65.82
88%
20 Construction of Crematorium 1,096 24.16 19.25
80%
21 Cattle Shed 1,064 17.58 13.55
77%
22 Constr of Gabion 968 16.01 12.56
79%
23 Roof Water Harvesting on gov/panchayat bldg 961 3.18 2.36
74%
24 Repair & maint of Pond/ Tank 753 20.39 16.31
80%
25 Underground Dyke for Ground Water Recharge 709 90.16 80.55
89%
26 Terracing 558 15.32 12.63
82%
27 Construction of Play field 495 13.42 9.87
74%
28 Constr of Aganwadi 487 13.03 11.72
90%
29 Repair & maint of Water Harvesting Structures 330 9.08 7.76
86%
30 Goat Shelter 321 1.92 1.21
63%
31 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 309 15.12 12.13
80%
32 Constr of GP Bhawan 275 20.80 14.82
71%
33 Culvert 232 11.33 10.81
95%
34 Constr of Compound wall 231 14.38 12.48
87%
35 Repair & Maint of Community infrastructure 220 4.20 3.14
75%
36 Constr of Kitchen Shed 199 0.84 0.62
74%
37 Constr of Food Grain storage 185 4.66 4.09
88%
38 Repair & maint of Percolation Tank 171 10.62 8.95
84%
39 Community Sanitary Complex 163 0.74 0.69
93%
40 Construction of Spur 151 8.04 6.86
85%
41 Other Works 150 1.61 0.87
54%
42 Repair & Maint of Check Dam/Stop Dam 87 5.57 5.02
90%
43 Repair & maint of Road 83 7.45 6.88
92%
44 Construction of Embankment 79 5.77 5.43
94%
45 Works for Flood Control and Protection 69 3.57 3.39
95%
46 Poultry Shelter 54 0.76 0.58
77%
47 Repair & Maint of Bund 49 1.39 1.10
79%
48 Nursery Development 44 0.46 0.31
68%
49 Construction of building/workshed for SHG 40 1.02 0.82
81%
50 Grass Land Development 30 1.41 0.80
57%
51 Bio-Fertilizer 25 0.16 0.10
62%
52 Repaire and Maint of NADEP/Vermi Compost Pit 13 0.08 0.06
70%
53 Construction of Other Community Building/Assets 10 0.30 0.27
92%
54 Water Converation - Others 9 0.75 0.72
95%
55 Deepening / Desilting of Flood Channels 8 0.15 0.12
79%
56 Piggery Shelter 6 0.10 0.08
74%
57 Construction of Canal 5 0.85 0.77
90%
58 Strengthening of Embankment 3 0.07 0.04
60%
59 Construction of Fish Drying Infrastructure 2 0.02 0.01
75%
60 Lining of Canal 1 0.02 0.02
85%
61 Lift Irrigation 1 0.11 0.04
34%
62 Renovation of Canal 1 0.08 0.04
58%
63 Construction of Village Haats 1 0.03 0.00
11%
Total 2,81,707 4,561.17 3,019.76
All 63 rows (zero-value rows hidden) ⇩ Export to Excel