| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 105 | 0.19 | 0.19 | 98% |
| 2 | Constr of Cement Concrete Roads | 33 | 0.31 | 0.28 | 89% |
| 3 | Cattle Shed | 20 | 0.24 | 0.17 | 70% |
| 4 | Construction of Well | 20 | 0.47 | 0.45 | 97% |
| 5 | Construction of Road and Culvert | 16 | 1.01 | 0.59 | 58% |
| 6 | Construction of Percolation Tank | 8 | 0.24 | 0.19 | 79% |
| 7 | Farm Pond | 8 | 0.22 | 0.16 | 76% |
| 8 | Plantation | 5 | 0.10 | 0.02 | 20% |
| 9 | Construction of Check Dam/Stop Dam | 5 | 0.11 | 0.12 | 108% |
| 10 | Land Development | 4 | 0.09 | 0.09 | 97% |
| 11 | Well Recharge | 1 | 0.00 | 0.00 | 98% |
| 12 | Construction of Play field | 1 | 0.04 | 0.04 | 98% |
| 13 | Constr of Aganwadi | 1 | 0.02 | 0.01 | 71% |
| 14 | Culvert | 1 | 0.02 | 0.02 | 83% |
| 15 | Community Sanitary Complex | 1 | 0.01 | 0.01 | 100% |
| 16 | Construction of Crematorium | 1 | 0.02 | 0.02 | 89% |
| Total | 230 | 3.08 | 2.35 |