Scope
Works completed
180
Sanctioned (pure scheme)
₹95.34 L
Expenditure since inception
₹55.71 L

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
11 works
₹23.76 L sanctioned
₹3.21 L spent (13%)
02
Constr of Cement Concrete Roads
22 works
₹11.51 L sanctioned
₹9.77 L spent (85%)
03
Construction of Check Dam/Stop Dam
2 works
₹9.82 L sanctioned
₹1.29 L spent (13%)
04
Cattle Shed
6 works
₹7.93 L sanctioned
₹5.39 L spent (68%)
05
Construction of Road and Culvert
3 works
₹7.36 L sanctioned
₹5.44 L spent (74%)
06
Rural Housing
36 works
₹5.66 L sanctioned
₹5.63 L spent (100%)
07
Construction of Toilets
34 works
₹5.59 L sanctioned
₹4.82 L spent (86%)
08
Construction of NADEP/Vermi Compost Pit
39 works
₹4.92 L sanctioned
₹4.90 L spent (99%)
09
Construction of Crematorium
2 works
₹3.60 L sanctioned
₹3.47 L spent (96%)
10
Constr of Aganwadi
2 works
₹3.60 L sanctioned
₹2.33 L spent (65%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Construction of NADEP/Vermi Compost Pit 39 4.92 4.90
100%
2 Rural Housing 36 5.66 5.63
100%
3 Construction of Toilets 34 5.59 4.82
86%
4 Constr of Cement Concrete Roads 22 11.51 9.77
85%
5 Plantation 11 23.76 3.21
14%
6 Cattle Shed 6 7.93 5.39
68%
7 Construction of Recharge Pits 6 0.87 0.57
66%
8 Repair & maint of Road 5 0.28 0.28
101%
9 Construction of Road and Culvert 3 7.36 5.44
74%
10 Construction of Check Dam/Stop Dam 2 9.82 1.29
13%
11 Constr of Kitchen Shed 2 0.32 0.31
96%
12 Construction of Crematorium 2 3.60 3.47
96%
13 Constr of Aganwadi 2 3.60 2.33
65%
14 Terracing 1 0.42 0.21
51%
15 Community Sanitary Complex 1 0.44 0.44
100%
16 Construction of Play field 1 3.53 2.37
67%
17 Constr of GP Bhawan 1 1.18 1.04
88%
18 Repair & maint of Percolation Tank 1 1.27 1.17
92%
19 Repaire and Maint of NADEP/Vermi Compost Pit 1 0.12 0.11
91%
20 Construction of Tank 1 0.59 0.45
75%
21 Boulder Check/Gully Plug 1 0.50 0.41
81%
22 Constr of Compound wall 1 1.42 1.46
103%
23 Construction of Trench 1 0.65 0.65
100%
Total 180 95.34 55.71