MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-09-01 08:48:19.512575
to
to
Reset filters
Scope
Works completed
472
Sanctioned (pure scheme)
₹2.48 Cr
Expenditure since inception
₹1.45 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
15 works
₹41.92 L sanctioned
₹6.12 L spent (15%)
02
Construction of Road and Culvert
5 works
₹38.87 L sanctioned
₹17.63 L spent (45%)
03
Rural Housing
229 works
₹38.33 L sanctioned
₹37.86 L spent (99%)
04
Construction of Bund
12 works
₹26.50 L sanctioned
₹15.23 L spent (57%)
05
Constr of Cement Concrete Roads
27 works
₹26.46 L sanctioned
₹15.95 L spent (60%)
06
Land Development
7 works
₹14.62 L sanctioned
₹6.65 L spent (46%)
07
Construction of Percolation Tank
4 works
₹11.96 L sanctioned
₹7.48 L spent (63%)
08
Construction of Toilets
116 works
₹9.98 L sanctioned
₹10.04 L spent (101%)
09
Solid and Liquid Waste Management
25 works
₹7.73 L sanctioned
₹4.69 L spent (61%)
10
Farm Pond
2 works
₹6.25 L sanctioned
₹4.32 L spent (69%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 229 38.33 37.86
99%
2 Construction of Toilets 116 9.98 10.04
101%
3 Constr of Cement Concrete Roads 27 26.46 15.95
60%
4 Solid and Liquid Waste Management 25 7.73 4.69
61%
5 Plantation 15 41.92 6.12
15%
6 Construction of Bund 12 26.50 15.23
58%
7 Land Development 7 14.62 6.65
46%
8 Construction of NADEP/Vermi Compost Pit 6 2.30 2.20
95%
9 Construction of Road and Culvert 5 38.87 17.63
45%
10 Well Recharge 4 0.73 1.90
262%
11 Construction of Percolation Tank 4 11.96 7.48
63%
12 Repair & maint of Water Harvesting Structures 2 1.18 0.56
47%
13 Community Sanitary Complex 2 0.90 0.83
92%
14 Repair & Maint of Check Dam/Stop Dam 2 0.94 0.45
48%
15 Construction of Tank 2 6.06 2.83
47%
16 Farm Pond 2 6.25 4.32
69%
17 Constr of Aganwadi 2 3.26 3.05
94%
18 Works for Flood Control and Protection 1 1.94 1.80
93%
19 Boulder Check/Gully Plug 1 0.47 0.14
30%
20 Constr of Compound wall 1 0.23 0.20
89%
21 Construction of Crematorium 1 1.80 1.80
100%
22 Construction of Play field 1 1.86 1.85
99%
23 Construction of Recharge Pits 1 0.11 0.10
89%
24 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.00 0.08
0%
25 Culvert 1 0.97 0.89
92%
26 Renovation of traditional water bodies 1 2.50 0.14
6%
27 Bio-Fertilizer 1 0.48 0.20
41%
Total 472 248.34 144.99
All 27 rows (zero-value rows hidden) ⇩ Export to Excel