| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 868 | 2.29 | 0.28 | 12% |
| 2 | Construction of Check Dam/Stop Dam | 13 | 0.54 | 0.01 | 2% |
| 3 | Construction of Well | 8 | 0.29 | 0.00 | 0% |
| 4 | Farm Pond | 8 | 0.25 | 0.00 | 0% |
| 5 | Construction of Percolation Tank | 5 | 0.10 | 0.00 | 0% |
| 6 | Plantation | 3 | 0.04 | 0.00 | 1% |
| 7 | Construction of Trench | 2 | 0.15 | 0.00 | 0% |
| 8 | Construction of Tank | 2 | 0.20 | 0.00 | 0% |
| 9 | Repair & maint of Road | 1 | 0.15 | 0.00 | 0% |
| 10 | Constr of Cement Concrete Roads | 1 | 0.00 | 0.00 | 0% |
| 11 | Construction of Bund | 1 | 0.04 | 0.00 | 0% |
| 12 | Well Recharge | 1 | 0.05 | 0.00 | 0% |
| Total | 913 | 4.11 | 0.29 |