Showcase — Completed Works

Rollup last refreshed: 2026-09-16 08:34:45.218851
to
to
Reset filters
Scope
Works completed
669
Sanctioned (pure scheme)
₹7.68 Cr
Expenditure since inception
₹7.02 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Land Development
125 works
₹1.23 Cr sanctioned
₹57.55 L spent (47%)
02
Construction of Check Dam/Stop Dam
89 works
₹1.11 Cr sanctioned
₹1.61 Cr spent (145%)
03
Culvert
7 works
₹1.00 Cr sanctioned
₹92.87 L spent (93%)
04
Farm Pond
27 works
₹54.06 L sanctioned
₹53.11 L spent (98%)
05
Plantation
19 works
₹49.21 L sanctioned
₹23.47 L spent (48%)
06
Rural Housing
257 works
₹47.35 L sanctioned
₹43.82 L spent (93%)
07
Construction of Tank
3 works
₹42.76 L sanctioned
₹38.15 L spent (89%)
08
Construction of Well
17 works
₹35.00 L sanctioned
₹18.70 L spent (53%)
09
Construction of Road and Culvert
15 works
₹31.07 L sanctioned
₹66.82 L spent (215%)
10
Construction of Trench
12 works
₹29.46 L sanctioned
₹29.51 L spent (100%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 257 0.47 0.44
93%
2 Land Development 125 1.23 0.58
47%
3 Construction of Check Dam/Stop Dam 89 1.11 1.61
145%
4 Farm Pond 27 0.54 0.53
98%
5 Plantation 19 0.49 0.23
48%
6 Construction of Well 17 0.35 0.19
53%
7 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 16 0.10 0.08
85%
8 Construction of Road and Culvert 15 0.31 0.67
215%
9 Cattle Shed 15 0.13 0.12
90%
10 Constr of Cement Concrete Roads 14 0.13 0.08
64%
11 Construction of Trench 12 0.29 0.30
100%
12 Well Recharge 9 0.16 0.09
57%
13 Construction of Bund 7 0.06 0.06
97%
14 Culvert 7 1.00 0.93
93%
15 Construction of Toilets 5 0.02 0.02
81%
16 Construction of NADEP/Vermi Compost Pit 5 0.02 0.02
78%
17 Repair & maint of Pond/ Tank 4 0.25 0.20
82%
18 Construction of Recharge Pits 3 0.04 0.03
61%
19 Construction of Percolation Tank 3 0.00 0.03
0%
20 Construction of Tank 3 0.43 0.38
89%
21 Terracing 2 0.18 0.09
48%
22 Construction of Crematorium 2 0.07 0.06
92%
23 Solid and Liquid Waste Management 2 0.00 0.00
22%
24 Community Sanitary Complex 2 0.01 0.01
67%
25 Strengthening of Embankment 2 0.05 0.10
194%
26 Boulder Check/Gully Plug 1 0.03 0.03
96%
27 Construction of Fish Drying Infrastructure 1 0.01 0.01
89%
28 Goat Shelter 1 0.00 0.00
93%
29 Constr of Kitchen Shed 1 0.00 0.00
87%
30 Renovation of Canal 1 0.10 0.08
78%
31 Repair & Maint of Bund 1 0.04 0.03
89%
32 Repair & Maint of Canal 1 0.05 0.04
92%
Total 669 7.68 7.02