Showcase — Completed Works

Rollup last refreshed: 2026-09-01 08:48:19.512575
to
to
Reset filters
Scope
Works completed
1,097
Sanctioned (pure scheme)
₹11.60 Cr
Expenditure since inception
₹8.32 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
104 works
₹1.98 Cr sanctioned
₹1.32 Cr spent (67%)
02
Construction of Road and Culvert
27 works
₹1.97 Cr sanctioned
₹1.54 Cr spent (78%)
03
Plantation
31 works
₹1.44 Cr sanctioned
₹45.90 L spent (32%)
04
Land Development
145 works
₹1.39 Cr sanctioned
₹1.10 Cr spent (79%)
05
Construction of Trench
108 works
₹1.14 Cr sanctioned
₹1.10 Cr spent (96%)
06
Construction of Bund
158 works
₹83.11 L sanctioned
₹58.87 L spent (71%)
07
Rural Housing
257 works
₹49.32 L sanctioned
₹45.06 L spent (91%)
08
Farm Pond
81 works
₹41.63 L sanctioned
₹31.43 L spent (76%)
09
Constr of Cement Concrete Roads
13 works
₹37.74 L sanctioned
₹36.46 L spent (97%)
10
Repair & maint of Road
4 works
₹31.28 L sanctioned
₹29.86 L spent (95%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 257 0.49 0.45
91%
2 Construction of Bund 158 0.83 0.59
71%
3 Land Development 145 1.39 1.10
79%
4 Construction of Trench 108 1.14 1.10
96%
5 Construction of Check Dam/Stop Dam 104 1.98 1.32
67%
6 Construction of NADEP/Vermi Compost Pit 92 0.17 0.14
80%
7 Farm Pond 81 0.42 0.31
76%
8 Plantation 31 1.44 0.46
32%
9 Construction of Road and Culvert 27 1.97 1.54
78%
10 Terracing 19 0.11 0.08
73%
11 Construction of Toilets 14 0.01 0.00
75%
12 Constr of Cement Concrete Roads 13 0.38 0.36
97%
13 Construction of Well 10 0.22 0.03
14%
14 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 6 0.02 0.02
76%
15 Goat Shelter 4 0.03 0.02
74%
16 Repair & maint of Road 4 0.31 0.30
96%
17 Construction of Percolation Tank 4 0.09 0.05
56%
18 Construction of Play field 4 0.09 0.03
35%
19 Construction of Recharge Pits 4 0.15 0.13
82%
20 Boulder Check/Gully Plug 3 0.04 0.04
83%
21 Repair & Maint of Check Dam/Stop Dam 2 0.09 0.06
66%
22 Community Sanitary Complex 2 0.01 0.01
62%
23 Well Recharge 2 0.02 0.01
64%
24 Repair & Maint of Community infrastructure 1 0.15 0.14
96%
25 Construction of Tank 1 0.04 0.03
88%
26 Solid and Liquid Waste Management 1 0.00 0.00
32%
Total 1,097 11.60 8.32
All 26 rows (zero-value rows hidden) ⇩ Export to Excel