MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-09-10 07:02:43.339169
to
to
Reset filters
Scope
Works completed
600
Sanctioned (pure scheme)
₹5.58 Cr
Expenditure since inception
₹4.30 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
93 works
₹1.61 Cr sanctioned
₹1.37 Cr spent (85%)
02
Farm Pond
44 works
₹1.05 Cr sanctioned
₹82.89 L spent (79%)
03
Land Development
245 works
₹74.13 L sanctioned
₹60.82 L spent (82%)
04
Construction of Road and Culvert
10 works
₹54.06 L sanctioned
₹26.25 L spent (49%)
05
Plantation
8 works
₹30.17 L sanctioned
₹5.70 L spent (19%)
06
Rural Housing
125 works
₹22.49 L sanctioned
₹22.01 L spent (98%)
07
Construction of Check Dam/Stop Dam
6 works
₹21.39 L sanctioned
₹30.46 L spent (142%)
08
Constr of Cement Concrete Roads
13 works
₹14.99 L sanctioned
₹11.08 L spent (74%)
09
Constr of Compound wall
1 works
₹14.76 L sanctioned
₹12.46 L spent (84%)
10
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
10 works
₹13.91 L sanctioned
₹11.55 L spent (83%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Land Development 245 0.74 0.61
82%
2 Rural Housing 125 0.22 0.22
98%
3 Construction of Bund 93 1.61 1.37
85%
4 Farm Pond 44 1.05 0.83
79%
5 Constr of Cement Concrete Roads 13 0.15 0.11
74%
6 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 10 0.14 0.12
83%
7 Construction of Road and Culvert 10 0.54 0.26
49%
8 Cattle Shed 8 0.05 0.01
19%
9 Plantation 8 0.30 0.06
19%
10 Construction of NADEP/Vermi Compost Pit 7 0.05 0.04
75%
11 Construction of Check Dam/Stop Dam 6 0.21 0.30
142%
12 Construction of Toilets 6 0.01 0.01
100%
13 Well Recharge 4 0.01 0.01
70%
14 Boulder Check/Gully Plug 3 0.04 0.06
139%
15 Goat Shelter 3 0.02 0.00
1%
16 Poultry Shelter 3 0.02 0.01
34%
17 Construction of Trench 3 0.05 0.04
85%
18 Renovation of traditional water bodies 2 0.08 0.07
81%
19 Construction of Well 2 0.04 0.02
49%
20 Constr of GP Bhawan 2 0.05 0.04
78%
21 Constr of Compound wall 1 0.15 0.12
84%
22 Water Converation - Others 1 0.01 0.00
14%
23 Underground Dyke for Ground Water Recharge 1 0.05 0.01
13%
Total 600 5.58 4.30
All 23 rows (zero-value rows hidden) ⇩ Export to Excel