MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-09-01 08:48:19.512575
to
to
Reset filters
Scope
Works completed
312
Sanctioned (pure scheme)
₹2.89 Cr
Expenditure since inception
₹3.12 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
26 works
₹59.44 L sanctioned
₹71.35 L spent (120%)
02
Constr of Cement Concrete Roads
23 works
₹56.28 L sanctioned
₹78.73 L spent (140%)
03
Rural Housing
168 works
₹30.43 L sanctioned
₹31.34 L spent (103%)
04
Construction of Road and Culvert
11 works
₹24.39 L sanctioned
₹40.80 L spent (167%)
05
Construction of Tank
2 works
₹17.71 L sanctioned
₹15.09 L spent (85%)
06
Land Development
25 works
₹15.48 L sanctioned
₹11.23 L spent (73%)
07
Repair & maint of Pond/ Tank
1 works
₹14.21 L sanctioned
₹8.61 L spent (61%)
08
Plantation
6 works
₹11.83 L sanctioned
₹3.76 L spent (32%)
09
Construction of Well
7 works
₹10.30 L sanctioned
₹5.05 L spent (49%)
10
Construction of Play field
1 works
₹9.90 L sanctioned
₹9.12 L spent (92%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 168 30.43 31.34
103%
2 Construction of Check Dam/Stop Dam 26 59.44 71.35
120%
3 Land Development 25 15.48 11.23
73%
4 Constr of Cement Concrete Roads 23 56.28 78.73
140%
5 Construction of Road and Culvert 11 24.39 40.80
167%
6 Construction of Well 7 10.30 5.05
49%
7 Nursery Development 6 4.06 2.62
65%
8 Plantation 6 11.83 3.76
32%
9 Construction of Percolation Tank 5 4.01 7.76
194%
10 Boulder Check/Gully Plug 4 1.26 1.13
90%
11 Construction of Trench 4 6.71 5.62
84%
12 Well Recharge 4 0.84 0.26
31%
13 Construction of Bund 3 7.04 6.46
92%
14 Construction of Recharge Pits 3 0.63 0.12
18%
15 Construction of Tank 2 17.71 15.09
85%
16 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 2 2.00 1.64
82%
17 Constr of Gabion 2 0.00 2.28
0%
18 Terracing 2 2.80 1.93
69%
19 Community Sanitary Complex 2 1.78 1.12
63%
20 Construction of Play field 1 9.90 9.12
92%
21 Construction of Crematorium 1 2.45 2.44
100%
22 Farm Pond 1 1.00 0.50
50%
23 Repair & Maint of Community infrastructure 1 2.00 0.00
0%
24 Repair & maint of Pond/ Tank 1 14.21 8.61
61%
25 Repair & maint of Road 1 1.35 1.03
76%
26 Solid and Liquid Waste Management 1 1.55 1.55
100%
Total 312 289.45 311.54
All 26 rows (zero-value rows hidden) ⇩ Export to Excel