| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 28 | 0.05 | 0.05 | 89% |
| 2 | Constr of Cement Concrete Roads | 24 | 0.19 | 0.17 | 92% |
| 3 | Construction of Tank | 14 | 1.71 | 1.53 | 90% |
| 4 | Cattle Shed | 8 | 0.07 | 0.07 | 99% |
| 5 | Construction of Percolation Tank | 7 | 0.57 | 0.55 | 96% |
| 6 | Construction of Road and Culvert | 6 | 0.93 | 0.52 | 56% |
| 7 | Land Development | 5 | 0.06 | 0.05 | 87% |
| 8 | Works for Flood Control and Protection | 4 | 0.25 | 0.20 | 80% |
| 9 | Constr of Aganwadi | 2 | 0.07 | 0.06 | 91% |
| 10 | Construction of Play field | 2 | 0.06 | 0.06 | 94% |
| 11 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 2 | 0.26 | 0.23 | 87% |
| 12 | Plantation | 2 | 0.07 | 0.00 | 7% |
| 13 | Construction of Crematorium | 2 | 0.04 | 0.04 | 101% |
| 14 | Construction of Bund | 1 | 0.01 | 0.00 | 9% |
| 15 | Construction of Trench | 1 | 0.01 | 0.01 | 59% |
| 16 | Constr of GP Bhawan | 1 | 0.05 | 0.05 | 99% |
| 17 | Construction of Check Dam/Stop Dam | 1 | 0.12 | 0.09 | 77% |
| 18 | Construction of Canal | 1 | 0.02 | 0.01 | 97% |
| Total | 111 | 4.52 | 3.69 |