Works completed
404
Sanctioned (pure scheme)
₹3.85 Cr
Expenditure since inception
₹2.76 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
35 works
₹78.43 L sanctioned
₹47.61 L spent (61%)
02
Construction of Road and Culvert
8 works
₹78.40 L sanctioned
₹38.15 L spent (49%)
03
Rural Housing
237 works
₹49.81 L sanctioned
₹47.10 L spent (95%)
04
Construction of Trench
3 works
₹33.54 L sanctioned
₹28.69 L spent (86%)
05
Construction of Play field
3 works
₹21.78 L sanctioned
₹18.39 L spent (84%)
06
Constr of Cement Concrete Roads
11 works
₹21.25 L sanctioned
₹20.08 L spent (95%)
07
Construction of Check Dam/Stop Dam
4 works
₹17.59 L sanctioned
₹15.32 L spent (87%)
08
Construction of Well
9 works
₹15.43 L sanctioned
₹10.65 L spent (69%)
09
Constr of Aganwadi
8 works
₹11.39 L sanctioned
₹11.33 L spent (100%)
10
Land Development
11 works
₹10.92 L sanctioned
₹5.79 L spent (53%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 237 49.81 47.10
95%
2 Boulder Check/Gully Plug 41 8.63 4.78
55%
3 Plantation 35 78.43 47.61
61%
4 Constr of Cement Concrete Roads 11 21.25 20.08
95%
5 Land Development 11 10.92 5.79
53%
6 Construction of NADEP/Vermi Compost Pit 10 1.27 1.09
86%
7 Construction of Well 9 15.43 10.65
69%
8 Construction of Road and Culvert 8 78.40 38.15
49%
9 Constr of Aganwadi 8 11.39 11.33
100%
10 Cattle Shed 8 7.52 6.89
92%
11 Roof Water Harvesting on gov/panchayat bldg 5 1.11 0.54
49%
12 Construction of Check Dam/Stop Dam 4 17.59 15.32
87%
13 Construction of Trench 3 33.54 28.69
86%
14 Construction of Play field 3 21.78 18.39
84%
15 Repair & maint of Water Harvesting Structures 3 0.77 0.59
77%
16 Repair & maint of Pond/ Tank 2 5.59 2.88
52%
17 Farm Pond 2 2.28 1.31
57%
18 Goat Shelter 1 0.97 0.90
93%
19 Construction of Canal 1 8.70 8.35
96%
20 Construction of Bund 1 4.96 5.04
102%
21 Renovation of traditional water bodies 1 4.53 0.48
11%
Total 404 384.89 275.94