MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-08-09 08:33:24.811433
to
to
Reset filters
Scope
Works completed
261
Sanctioned (pure scheme)
₹12.35 Cr
Expenditure since inception
₹10.98 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Works for Flood Control and Protection
39 works
₹5.18 Cr sanctioned
₹4.74 Cr spent (92%)
02
Construction of Road and Culvert
15 works
₹1.68 Cr sanctioned
₹1.46 Cr spent (87%)
03
Plantation
14 works
₹99.17 L sanctioned
₹87.02 L spent (88%)
04
Culvert
5 works
₹62.59 L sanctioned
₹59.54 L spent (95%)
05
Construction of Bund
6 works
₹61.56 L sanctioned
₹53.68 L spent (87%)
06
Construction of Tank
6 works
₹51.00 L sanctioned
₹41.36 L spent (81%)
07
Construction of Check Dam/Stop Dam
5 works
₹45.91 L sanctioned
₹40.31 L spent (88%)
08
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
5 works
₹44.57 L sanctioned
₹38.43 L spent (86%)
09
Cattle Shed
5 works
₹40.67 L sanctioned
₹37.54 L spent (92%)
10
Construction of Percolation Tank
3 works
₹32.46 L sanctioned
₹22.48 L spent (69%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 65 0.10 0.10
97%
2 Construction of Toilets 43 0.02 0.02
87%
3 Works for Flood Control and Protection 39 5.18 4.74
92%
4 Construction of Road and Culvert 15 1.68 1.46
87%
5 Plantation 14 0.99 0.87
88%
6 Construction of Recharge Pits 10 0.11 0.10
91%
7 Roof Water Harvesting on gov/panchayat bldg 10 0.14 0.08
58%
8 Constr of Cement Concrete Roads 9 0.08 0.09
120%
9 Construction of Tank 6 0.51 0.41
81%
10 Construction of Crematorium 6 0.14 0.11
81%
11 Construction of Bund 6 0.62 0.54
87%
12 Farm Pond 6 0.04 0.03
77%
13 Culvert 5 0.63 0.60
95%
14 Cattle Shed 5 0.41 0.38
92%
15 Construction of Check Dam/Stop Dam 5 0.46 0.40
88%
16 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 5 0.45 0.38
86%
17 Constr of Aganwadi 3 0.05 0.05
99%
18 Construction of Percolation Tank 3 0.32 0.22
69%
19 Constr of Gabion 1 0.15 0.14
94%
20 Construction of Play field 1 0.03 0.02
61%
21 Grass Land Development 1 0.08 0.05
65%
22 Land Development 1 0.05 0.05
92%
23 Repair & maint of Pond/ Tank 1 0.13 0.12
97%
24 Community Sanitary Complex 1 0.00 0.00
100%
Total 261 12.35 10.98
All 24 rows (zero-value rows hidden) ⇩ Export to Excel