Showcase — Completed Works

Rollup last refreshed: 2026-09-06 07:04:10.165253
to
to
Reset filters
Scope
Works completed
151
Sanctioned (pure scheme)
₹3.06 Cr
Expenditure since inception
₹2.34 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
11 works
₹1.08 Cr sanctioned
₹70.97 L spent (66%)
02
Cattle Shed
20 works
₹58.76 L sanctioned
₹53.14 L spent (90%)
03
Construction of Check Dam/Stop Dam
5 works
₹47.16 L sanctioned
₹41.70 L spent (88%)
04
Plantation
5 works
₹24.74 L sanctioned
₹10.89 L spent (44%)
05
Construction of Tank
1 works
₹14.80 L sanctioned
₹11.79 L spent (80%)
06
Constr of Cement Concrete Roads
11 works
₹14.01 L sanctioned
₹12.42 L spent (89%)
07
Constr of Aganwadi
3 works
₹12.39 L sanctioned
₹12.41 L spent (100%)
08
Constr of Kitchen Shed
1 works
₹4.25 L sanctioned
₹4.29 L spent (101%)
09
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
1 works
₹4.16 L sanctioned
₹1.91 L spent (46%)
10
Construction of Other Community Building/Assets
2 works
₹3.60 L sanctioned
₹3.21 L spent (89%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Solid and Liquid Waste Management 42 0.00 0.00
93%
2 Rural Housing 20 0.03 0.03
85%
3 Cattle Shed 20 0.59 0.53
90%
4 Constr of Cement Concrete Roads 11 0.14 0.12
89%
5 Construction of Road and Culvert 11 1.08 0.71
66%
6 Land Development 9 0.01 0.01
120%
7 Construction of Recharge Pits 7 0.00 0.00
97%
8 Construction of Check Dam/Stop Dam 5 0.47 0.42
88%
9 Plantation 5 0.25 0.11
44%
10 Farm Pond 4 0.01 0.01
89%
11 Repair & maint of Road 4 0.03 0.02
68%
12 Constr of Aganwadi 3 0.12 0.12
100%
13 Construction of Other Community Building/Assets 2 0.04 0.03
89%
14 Works for Flood Control and Protection 1 0.02 0.02
84%
15 Constr of Kitchen Shed 1 0.04 0.04
101%
16 Construction of Bund 1 0.00 0.00
82%
17 Construction of NADEP/Vermi Compost Pit 1 0.00 0.00
132%
18 Construction of Percolation Tank 1 0.03 0.01
41%
19 Construction of Tank 1 0.15 0.12
80%
20 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.04 0.02
46%
21 Repair & Maint of Community infrastructure 1 0.00 0.00
7%
Total 151 3.06 2.34