MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
203
Sanctioned (pure scheme)
₹3.06 Cr
Expenditure since inception
₹2.11 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
25 works
₹83.48 L sanctioned
₹58.46 L spent (70%)
02
Construction of Road and Culvert
11 works
₹51.61 L sanctioned
₹32.51 L spent (63%)
03
Construction of Bund
26 works
₹30.33 L sanctioned
₹26.61 L spent (88%)
04
Land Development
29 works
₹26.26 L sanctioned
₹19.07 L spent (73%)
05
Plantation
8 works
₹24.08 L sanctioned
₹2.42 L spent (10%)
06
Construction of Percolation Tank
2 works
₹17.80 L sanctioned
₹16.33 L spent (92%)
07
Constr of Cement Concrete Roads
10 works
₹12.30 L sanctioned
₹8.99 L spent (73%)
08
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
2 works
₹11.94 L sanctioned
₹9.93 L spent (83%)
09
Rural Housing
68 works
₹10.59 L sanctioned
₹10.23 L spent (97%)
10
Construction of Well
5 works
₹9.88 L sanctioned
₹3.95 L spent (40%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 68 10.59 10.23
97%
2 Land Development 29 26.26 19.07
73%
3 Construction of Bund 26 30.33 26.61
88%
4 Construction of Check Dam/Stop Dam 25 83.48 58.46
70%
5 Construction of Road and Culvert 11 51.61 32.51
63%
6 Constr of Cement Concrete Roads 10 12.30 8.99
73%
7 Plantation 8 24.08 2.42
10%
8 Construction of Well 5 9.88 3.95
40%
9 Construction of Crematorium 3 5.40 2.18
40%
10 Construction of Trench 3 1.32 2.12
160%
11 Repair & Maint of Community infrastructure 3 0.00 0.07
0%
12 Construction of Percolation Tank 2 17.80 16.33
92%
13 Repair & Maint of Bund 2 0.72 0.67
93%
14 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 2 11.94 9.93
83%
15 Works for Flood Control and Protection 1 7.06 7.01
99%
16 Constr of Aganwadi 1 3.30 3.38
102%
17 Construction of Play field 1 3.53 1.44
41%
18 Construction of Tank 1 4.56 3.70
81%
19 Farm Pond 1 1.05 0.95
90%
20 Renovation of traditional water bodies 1 0.78 0.75
97%
Total 203 305.99 210.77
All 20 rows (zero-value rows hidden) ⇩ Export to Excel