Showcase — Completed Works

Rollup last refreshed: 2026-09-10 07:02:43.339169
to
to
Reset filters
Scope
Works completed
317
Sanctioned (pure scheme)
₹3.94 Cr
Expenditure since inception
₹3.25 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
15 works
₹92.25 L sanctioned
₹85.91 L spent (93%)
02
Construction of Road and Culvert
23 works
₹78.79 L sanctioned
₹62.89 L spent (80%)
03
Construction of Trench
19 works
₹55.09 L sanctioned
₹42.24 L spent (77%)
04
Constr of Cement Concrete Roads
44 works
₹28.84 L sanctioned
₹19.27 L spent (67%)
05
Plantation
13 works
₹28.22 L sanctioned
₹20.97 L spent (74%)
06
Cattle Shed
31 works
₹19.75 L sanctioned
₹17.86 L spent (90%)
07
Construction of NADEP/Vermi Compost Pit
73 works
₹14.53 L sanctioned
₹12.49 L spent (86%)
08
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
1 works
₹14.14 L sanctioned
₹14.12 L spent (100%)
09
Construction of Check Dam/Stop Dam
8 works
₹13.98 L sanctioned
₹5.93 L spent (42%)
10
Construction of Crematorium
2 works
₹8.35 L sanctioned
₹6.32 L spent (76%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Construction of NADEP/Vermi Compost Pit 73 14.53 12.49
86%
2 Constr of Cement Concrete Roads 44 28.84 19.27
67%
3 Construction of Toilets 44 3.13 2.99
96%
4 Cattle Shed 31 19.75 17.86
90%
5 Construction of Road and Culvert 23 78.79 62.89
80%
6 Rural Housing 21 3.49 3.04
87%
7 Construction of Trench 19 55.09 42.24
77%
8 Construction of Bund 15 92.25 85.91
93%
9 Plantation 13 28.22 20.97
74%
10 Construction of Check Dam/Stop Dam 8 13.98 5.93
42%
11 Construction of Tank 3 0.59 0.39
67%
12 Constr of Compound wall 3 0.42 0.38
92%
13 Solid and Liquid Waste Management 3 1.27 1.23
97%
14 Well Recharge 2 1.87 1.79
96%
15 Construction of Crematorium 2 8.35 6.32
76%
16 Repair & Maint of Bund 2 8.19 8.14
99%
17 Boulder Check/Gully Plug 2 7.99 7.76
97%
18 Construction of Spur 1 0.58 0.56
97%
19 Construction of Other Community Building/Assets 1 0.18 0.17
96%
20 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 14.14 14.12
100%
21 Farm Pond 1 0.00 0.30
0%
22 Land Development 1 5.00 4.00
80%
23 Constr of Gabion 1 2.11 2.07
98%
24 Underground Dyke for Ground Water Recharge 1 3.95 3.24
82%
25 Repair & Maint of Community infrastructure 1 0.20 0.18
93%
26 Repair & maint of Pond/ Tank 1 1.14 1.13
99%
Total 317 394.05 325.38
All 26 rows (zero-value rows hidden) ⇩ Export to Excel