Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
490
Sanctioned (pure scheme)
₹3.98 Cr
Expenditure since inception
₹2.49 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
64 works
₹1.01 Cr sanctioned
₹54.43 L spent (54%)
02
Construction of Road and Culvert
15 works
₹57.85 L sanctioned
₹28.50 L spent (49%)
03
Construction of Check Dam/Stop Dam
11 works
₹53.92 L sanctioned
₹42.10 L spent (78%)
04
Constr of Cement Concrete Roads
30 works
₹35.54 L sanctioned
₹9.96 L spent (28%)
05
Land Development
49 works
₹30.58 L sanctioned
₹22.60 L spent (74%)
06
Construction of Trench
4 works
₹20.14 L sanctioned
₹12.08 L spent (60%)
07
Construction of Toilets
182 works
₹19.06 L sanctioned
₹16.61 L spent (87%)
08
Construction of Percolation Tank
1 works
₹14.98 L sanctioned
₹11.65 L spent (78%)
09
Cattle Shed
21 works
₹14.19 L sanctioned
₹13.61 L spent (96%)
10
Construction of Crematorium
1 works
₹13.54 L sanctioned
₹7.18 L spent (53%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Construction of Toilets 182 0.19 0.17
87%
2 Plantation 64 1.01 0.54
54%
3 Construction of NADEP/Vermi Compost Pit 54 0.07 0.06
80%
4 Land Development 49 0.31 0.23
74%
5 Rural Housing 38 0.09 0.07
74%
6 Constr of Cement Concrete Roads 30 0.36 0.10
28%
7 Cattle Shed 21 0.14 0.14
96%
8 Construction of Road and Culvert 15 0.58 0.28
49%
9 Construction of Check Dam/Stop Dam 11 0.54 0.42
78%
10 Construction of Recharge Pits 6 0.01 0.01
98%
11 Construction of Trench 4 0.20 0.12
60%
12 Solid and Liquid Waste Management 3 0.02 0.02
96%
13 Farm Pond 2 0.01 0.01
49%
14 Repair & maint of Road 2 0.01 0.01
96%
15 Repair & maint of Pond/ Tank 2 0.06 0.05
85%
16 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.01 0.00
66%
17 Nursery Development 1 0.00 0.00
74%
18 Construction of Bund 1 0.07 0.06
89%
19 Construction of Crematorium 1 0.14 0.07
53%
20 Construction of Percolation Tank 1 0.15 0.12
78%
21 Construction of Tank 1 0.01 0.01
78%
22 Constr of Aganwadi 1 0.01 0.00
58%
Total 490 3.98 2.49
All 22 rows (zero-value rows hidden) ⇩ Export to Excel