MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
199
Sanctioned (pure scheme)
₹2.05 Cr
Expenditure since inception
₹1.17 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
6 works
₹62.50 L sanctioned
₹22.68 L spent (36%)
02
Construction of Check Dam/Stop Dam
7 works
₹23.28 L sanctioned
₹20.02 L spent (86%)
03
Plantation
10 works
₹22.23 L sanctioned
₹6.33 L spent (28%)
04
Construction of Bund
9 works
₹17.81 L sanctioned
₹10.33 L spent (58%)
05
Rural Housing
95 works
₹15.56 L sanctioned
₹14.46 L spent (93%)
06
Farm Pond
10 works
₹13.34 L sanctioned
₹8.27 L spent (62%)
07
Constr of Cement Concrete Roads
26 works
₹12.66 L sanctioned
₹10.03 L spent (79%)
08
Construction of Tank
3 works
₹8.85 L sanctioned
₹6.25 L spent (71%)
09
Construction of Percolation Tank
2 works
₹6.89 L sanctioned
₹3.72 L spent (54%)
10
Repair & maint of Pond/ Tank
1 works
₹4.13 L sanctioned
₹2.10 L spent (51%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 95 15.56 14.46
93%
2 Constr of Cement Concrete Roads 26 12.66 10.03
79%
3 Farm Pond 10 13.34 8.27
62%
4 Plantation 10 22.23 6.33
29%
5 Construction of NADEP/Vermi Compost Pit 10 1.48 1.36
92%
6 Construction of Bund 9 17.81 10.33
58%
7 Construction of Check Dam/Stop Dam 7 23.28 20.02
86%
8 Construction of Road and Culvert 6 62.50 22.68
36%
9 Terracing 3 1.49 1.14
76%
10 Construction of Trench 3 1.15 0.57
49%
11 Construction of Tank 3 8.85 6.25
71%
12 Cattle Shed 2 1.68 1.34
80%
13 Construction of Crematorium 2 3.60 3.44
95%
14 Construction of Percolation Tank 2 6.89 3.72
54%
15 Land Development 2 0.64 0.41
63%
16 Repair & maint of Pond/ Tank 1 4.13 2.10
51%
17 Construction of Play field 1 1.87 0.81
43%
18 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.66 0.65
98%
19 Well Recharge 1 0.26 0.13
48%
20 Constr of Aganwadi 1 1.16 1.15
100%
21 Construction of Toilets 1 0.12 0.12
97%
22 Other Works 1 0.49 0.32
67%
23 Construction of Well 1 2.28 1.02
45%
24 Renovation of traditional water bodies 1 0.50 0.37
74%
Total 199 204.64 116.99
All 24 rows (zero-value rows hidden) ⇩ Export to Excel