| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 158 | 26.70 | 25.94 | 97% |
| 2 | Construction of Check Dam/Stop Dam | 25 | 63.98 | 53.95 | 84% |
| 3 | Constr of Cement Concrete Roads | 20 | 42.69 | 27.03 | 63% |
| 4 | Construction of Road and Culvert | 8 | 37.67 | 32.15 | 85% |
| 5 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 7 | 34.40 | 27.07 | 79% |
| 6 | Construction of Well | 6 | 15.52 | 12.72 | 82% |
| 7 | Construction of Percolation Tank | 6 | 37.60 | 31.80 | 85% |
| 8 | Plantation | 5 | 6.61 | 3.42 | 52% |
| 9 | Construction of Bund | 4 | 19.12 | 16.47 | 86% |
| 10 | Culvert | 4 | 24.70 | 19.96 | 81% |
| 11 | Well Recharge | 3 | 8.62 | 6.84 | 79% |
| 12 | Construction of Trench | 3 | 7.26 | 6.25 | 86% |
| 13 | Fish Culture | 2 | 9.64 | 6.10 | 63% |
| 14 | Construction of Tank | 2 | 15.32 | 13.59 | 89% |
| 15 | Repair & maint of Pond/ Tank | 1 | 7.48 | 6.58 | 88% |
| 16 | Construction of Toilets | 1 | 0.75 | 0.36 | 49% |
| 17 | Construction of NADEP/Vermi Compost Pit | 1 | 1.22 | 0.15 | 12% |
| 18 | Constr of Aganwadi | 1 | 2.16 | 1.97 | 91% |
| 19 | Farm Pond | 1 | 10.54 | 10.39 | 99% |
| 20 | Repair & Maint of Check Dam/Stop Dam | 1 | 14.75 | 13.49 | 92% |
| 21 | Construction of Crematorium | 1 | 14.56 | 13.14 | 90% |
| Total | 260 | 401.28 | 329.38 |