| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 344 | 57.28 | 56.87 | 99% |
| 2 | Farm Pond | 23 | 9.91 | 7.05 | 71% |
| 3 | Construction of Bund | 19 | 19.80 | 15.56 | 79% |
| 4 | Construction of Well | 17 | 33.12 | 22.98 | 69% |
| 5 | Constr of Cement Concrete Roads | 17 | 26.64 | 19.72 | 74% |
| 6 | Construction of Recharge Pits | 11 | 13.58 | 11.97 | 88% |
| 7 | Construction of Toilets | 11 | 0.79 | 0.73 | 93% |
| 8 | Construction of Trench | 10 | 44.57 | 38.84 | 87% |
| 9 | Plantation | 9 | 10.36 | 9.65 | 93% |
| 10 | Construction of Percolation Tank | 5 | 12.45 | 10.85 | 87% |
| 11 | Construction of Check Dam/Stop Dam | 5 | 51.51 | 49.84 | 97% |
| 12 | Solid and Liquid Waste Management | 5 | 0.71 | 0.21 | 30% |
| 13 | Culvert | 3 | 2.40 | 2.33 | 97% |
| 14 | Construction of Road and Culvert | 3 | 11.38 | 8.71 | 77% |
| 15 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 2 | 0.66 | 0.45 | 67% |
| 16 | Constr of GP Bhawan | 2 | 2.68 | 2.46 | 92% |
| 17 | Repair & Maint of Community infrastructure | 1 | 2.00 | 2.00 | 100% |
| 18 | Land Development | 1 | 2.16 | 0.67 | 31% |
| 19 | Construction of Crematorium | 1 | 1.80 | 0.02 | 1% |
| Total | 489 | 303.80 | 260.92 |