| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 224 | 39.65 | 39.62 | 100% |
| 2 | Construction of Bund | 29 | 7.06 | 4.79 | 68% |
| 3 | Constr of Cement Concrete Roads | 22 | 20.96 | 16.38 | 78% |
| 4 | Construction of Toilets | 18 | 2.16 | 1.98 | 92% |
| 5 | Construction of Check Dam/Stop Dam | 15 | 33.38 | 29.24 | 88% |
| 6 | Farm Pond | 12 | 31.02 | 25.99 | 84% |
| 7 | Well Recharge | 10 | 12.21 | 8.04 | 66% |
| 8 | Construction of Road and Culvert | 9 | 40.91 | 10.32 | 25% |
| 9 | Cattle Shed | 3 | 1.91 | 1.84 | 96% |
| 10 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 3 | 0.93 | 0.36 | 39% |
| 11 | Construction of Crematorium | 2 | 5.75 | 5.65 | 98% |
| 12 | Renovation of traditional water bodies | 2 | 6.89 | 3.67 | 53% |
| 13 | Construction of Play field | 1 | 3.20 | 0.99 | 31% |
| 14 | Plantation | 1 | 3.35 | 0.43 | 13% |
| 15 | Culvert | 1 | 0.35 | 0.35 | 99% |
| Total | 352 | 209.74 | 149.64 |