MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
495
Sanctioned (pure scheme)
₹2.77 Cr
Expenditure since inception
₹2.28 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Farm Pond
22 works
₹75.98 L sanctioned
₹62.35 L spent (82%)
02
Rural Housing
369 works
₹64.27 L sanctioned
₹64.00 L spent (100%)
03
Construction of Bund
31 works
₹28.39 L sanctioned
₹23.93 L spent (84%)
04
Construction of Road and Culvert
3 works
₹24.71 L sanctioned
₹15.04 L spent (61%)
05
Construction of Check Dam/Stop Dam
15 works
₹21.91 L sanctioned
₹14.27 L spent (65%)
06
Constr of Cement Concrete Roads
16 works
₹16.00 L sanctioned
₹13.92 L spent (87%)
07
Construction of building/workshed for SHG
1 works
₹7.51 L sanctioned
₹7.50 L spent (100%)
08
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
6 works
₹5.10 L sanctioned
₹3.46 L spent (68%)
09
Repair & maint of Pond/ Tank
2 works
₹4.75 L sanctioned
₹4.67 L spent (98%)
10
Construction of Play field
1 works
₹4.48 L sanctioned
₹4.47 L spent (100%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 369 64.27 64.00
100%
2 Construction of Bund 31 28.39 23.93
84%
3 Farm Pond 22 75.98 62.35
82%
4 Constr of Cement Concrete Roads 16 16.00 13.92
87%
5 Construction of Check Dam/Stop Dam 15 21.91 14.27
65%
6 Well Recharge 9 3.79 1.54
41%
7 Construction of Toilets 7 0.84 0.82
97%
8 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 6 5.10 3.46
68%
9 Cattle Shed 5 4.17 3.92
94%
10 Construction of Road and Culvert 3 24.71 15.04
61%
11 Renovation of traditional water bodies 2 4.30 4.22
98%
12 Land Development 2 1.47 0.73
50%
13 Repair & maint of Pond/ Tank 2 4.75 4.67
98%
14 Plantation 1 3.86 0.36
9%
15 Construction of Play field 1 4.48 4.47
100%
16 Construction of Crematorium 1 2.85 2.43
85%
17 Construction of Well 1 2.51 0.12
5%
18 Construction of building/workshed for SHG 1 7.51 7.50
100%
19 Solid and Liquid Waste Management 1 0.31 0.31
100%
Total 495 277.21 228.06
All 19 rows (zero-value rows hidden) ⇩ Export to Excel