| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 369 | 64.27 | 64.00 | 100% |
| 2 | Construction of Bund | 31 | 28.39 | 23.93 | 84% |
| 3 | Farm Pond | 22 | 75.98 | 62.35 | 82% |
| 4 | Constr of Cement Concrete Roads | 16 | 16.00 | 13.92 | 87% |
| 5 | Construction of Check Dam/Stop Dam | 15 | 21.91 | 14.27 | 65% |
| 6 | Well Recharge | 9 | 3.79 | 1.54 | 41% |
| 7 | Construction of Toilets | 7 | 0.84 | 0.82 | 97% |
| 8 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 6 | 5.10 | 3.46 | 68% |
| 9 | Cattle Shed | 5 | 4.17 | 3.92 | 94% |
| 10 | Construction of Road and Culvert | 3 | 24.71 | 15.04 | 61% |
| 11 | Renovation of traditional water bodies | 2 | 4.30 | 4.22 | 98% |
| 12 | Land Development | 2 | 1.47 | 0.73 | 50% |
| 13 | Repair & maint of Pond/ Tank | 2 | 4.75 | 4.67 | 98% |
| 14 | Plantation | 1 | 3.86 | 0.36 | 9% |
| 15 | Construction of Play field | 1 | 4.48 | 4.47 | 100% |
| 16 | Construction of Crematorium | 1 | 2.85 | 2.43 | 85% |
| 17 | Construction of Well | 1 | 2.51 | 0.12 | 5% |
| 18 | Construction of building/workshed for SHG | 1 | 7.51 | 7.50 | 100% |
| 19 | Solid and Liquid Waste Management | 1 | 0.31 | 0.31 | 100% |
| Total | 495 | 277.21 | 228.06 |