Showcase — Completed Works

Rollup last refreshed: 2026-09-01 08:48:19.512575
to
to
Reset filters
Scope
Works completed
235
Sanctioned (pure scheme)
₹1.95 Cr
Expenditure since inception
₹1.43 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
8 works
₹44.59 L sanctioned
₹22.64 L spent (51%)
02
Rural Housing
140 works
₹24.15 L sanctioned
₹23.23 L spent (96%)
03
Constr of Cement Concrete Roads
21 works
₹21.84 L sanctioned
₹20.58 L spent (94%)
04
Construction of Check Dam/Stop Dam
10 works
₹19.39 L sanctioned
₹20.66 L spent (107%)
05
Construction of Well
4 works
₹12.67 L sanctioned
₹10.42 L spent (82%)
06
Construction of Trench
6 works
₹12.46 L sanctioned
₹8.47 L spent (68%)
07
Land Development
9 works
₹10.91 L sanctioned
₹3.74 L spent (34%)
08
Plantation
3 works
₹7.18 L sanctioned
₹37,049 spent (5%)
09
Farm Pond
2 works
₹7.01 L sanctioned
₹5.59 L spent (80%)
10
Construction of Percolation Tank
1 works
₹6.53 L sanctioned
₹6.44 L spent (99%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 140 24.15 23.23
96%
2 Constr of Cement Concrete Roads 21 21.84 20.58
94%
3 Construction of Check Dam/Stop Dam 10 19.39 20.66
107%
4 Construction of NADEP/Vermi Compost Pit 10 2.41 1.68
70%
5 Land Development 9 10.91 3.74
34%
6 Construction of Road and Culvert 8 44.59 22.64
51%
7 Construction of Tank 7 4.94 2.67
54%
8 Construction of Trench 6 12.46 8.47
68%
9 Cattle Shed 5 5.13 4.88
95%
10 Construction of Well 4 12.67 10.42
82%
11 Plantation 3 7.18 0.37
5%
12 Farm Pond 2 7.01 5.59
80%
13 Construction of Percolation Tank 1 6.53 6.44
99%
14 Construction of Play field 1 1.87 0.09
5%
15 Construction of Recharge Pits 1 0.12 0.09
78%
16 Constr of Aganwadi 1 1.80 1.24
69%
17 Constr of GP Bhawan 1 5.80 5.67
98%
18 Other Works 1 0.14 0.13
90%
19 Constr of Compound wall 1 0.38 0.28
73%
20 Construction of Bund 1 0.77 0.46
60%
21 Construction of Crematorium 1 2.45 1.81
74%
22 Solid and Liquid Waste Management 1 2.46 1.49
61%
Total 235 195.00 142.62
All 22 rows (zero-value rows hidden) ⇩ Export to Excel