| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 140 | 24.15 | 23.23 | 96% |
| 2 | Constr of Cement Concrete Roads | 21 | 21.84 | 20.58 | 94% |
| 3 | Construction of Check Dam/Stop Dam | 10 | 19.39 | 20.66 | 107% |
| 4 | Construction of NADEP/Vermi Compost Pit | 10 | 2.41 | 1.68 | 70% |
| 5 | Land Development | 9 | 10.91 | 3.74 | 34% |
| 6 | Construction of Road and Culvert | 8 | 44.59 | 22.64 | 51% |
| 7 | Construction of Tank | 7 | 4.94 | 2.67 | 54% |
| 8 | Construction of Trench | 6 | 12.46 | 8.47 | 68% |
| 9 | Cattle Shed | 5 | 5.13 | 4.88 | 95% |
| 10 | Construction of Well | 4 | 12.67 | 10.42 | 82% |
| 11 | Plantation | 3 | 7.18 | 0.37 | 5% |
| 12 | Farm Pond | 2 | 7.01 | 5.59 | 80% |
| 13 | Construction of Percolation Tank | 1 | 6.53 | 6.44 | 99% |
| 14 | Construction of Play field | 1 | 1.87 | 0.09 | 5% |
| 15 | Construction of Recharge Pits | 1 | 0.12 | 0.09 | 78% |
| 16 | Constr of Aganwadi | 1 | 1.80 | 1.24 | 69% |
| 17 | Constr of GP Bhawan | 1 | 5.80 | 5.67 | 98% |
| 18 | Other Works | 1 | 0.14 | 0.13 | 90% |
| 19 | Constr of Compound wall | 1 | 0.38 | 0.28 | 73% |
| 20 | Construction of Bund | 1 | 0.77 | 0.46 | 60% |
| 21 | Construction of Crematorium | 1 | 2.45 | 1.81 | 74% |
| 22 | Solid and Liquid Waste Management | 1 | 2.46 | 1.49 | 61% |
| Total | 235 | 195.00 | 142.62 |