| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 75 | 12.12 | 12.05 | 99% |
| 2 | Construction of Bund | 23 | 23.04 | 15.84 | 69% |
| 3 | Construction of NADEP/Vermi Compost Pit | 22 | 8.22 | 7.34 | 89% |
| 4 | Construction of Well | 17 | 52.56 | 45.60 | 87% |
| 5 | Constr of Cement Concrete Roads | 11 | 9.36 | 8.01 | 86% |
| 6 | Land Development | 8 | 14.46 | 4.33 | 30% |
| 7 | Plantation | 6 | 11.86 | 5.89 | 50% |
| 8 | Constr of Gabion | 6 | 6.36 | 3.84 | 60% |
| 9 | Boulder Check/Gully Plug | 6 | 6.09 | 3.33 | 55% |
| 10 | Well Recharge | 5 | 17.37 | 16.09 | 93% |
| 11 | Construction of Road and Culvert | 5 | 33.32 | 9.38 | 28% |
| 12 | Construction of Tank | 5 | 13.78 | 8.23 | 60% |
| 13 | Construction of Trench | 4 | 16.56 | 10.18 | 61% |
| 14 | Construction of Crematorium | 4 | 11.95 | 11.66 | 98% |
| 15 | Cattle Shed | 3 | 3.08 | 3.06 | 99% |
| 16 | Construction of Check Dam/Stop Dam | 2 | 2.97 | 2.88 | 97% |
| 17 | Construction of Recharge Pits | 2 | 0.29 | 0.19 | 64% |
| 18 | Constr of GP Bhawan | 1 | 12.85 | 9.74 | 76% |
| 19 | Construction of Play field | 1 | 1.87 | 0.36 | 19% |
| 20 | Solid and Liquid Waste Management | 1 | 0.25 | 0.25 | 99% |
| 21 | Constr of Compound wall | 1 | 0.55 | 0.52 | 95% |
| 22 | Constr of Aganwadi | 1 | 0.88 | 0.88 | 100% |
| 23 | Community Sanitary Complex | 1 | 0.44 | 0.44 | 101% |
| Total | 210 | 260.22 | 180.09 |