| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 236 | 0.40 | 0.39 | 98% |
| 2 | Construction of Well | 76 | 1.90 | 1.81 | 95% |
| 3 | Construction of Toilets | 43 | 0.03 | 0.02 | 81% |
| 4 | Constr of Cement Concrete Roads | 23 | 0.30 | 0.28 | 95% |
| 5 | Plantation | 6 | 0.14 | 0.03 | 19% |
| 6 | Land Development | 6 | 0.11 | 0.07 | 64% |
| 7 | Repair & maint of Pond/ Tank | 5 | 0.30 | 0.30 | 100% |
| 8 | Construction of Percolation Tank | 4 | 0.04 | 0.03 | 69% |
| 9 | Construction of Road and Culvert | 3 | 0.46 | 0.35 | 75% |
| 10 | Renovation of traditional water bodies | 3 | 0.09 | 0.11 | 121% |
| 11 | Farm Pond | 3 | 0.04 | 0.03 | 82% |
| 12 | Culvert | 3 | 0.06 | 0.06 | 92% |
| 13 | Roof Water Harvesting on gov/panchayat bldg | 2 | 0.01 | 0.01 | 80% |
| 14 | Construction of Bund | 2 | 0.04 | 0.02 | 42% |
| 15 | Construction of Crematorium | 2 | 0.05 | 0.05 | 98% |
| 16 | Community Sanitary Complex | 1 | 0.00 | 0.00 | 92% |
| 17 | Construction of Tank | 1 | 0.15 | 0.15 | 98% |
| 18 | Constr of Compound wall | 1 | 0.15 | 0.15 | 97% |
| 19 | Construction of Check Dam/Stop Dam | 1 | 0.03 | 0.02 | 65% |
| 20 | Constr of Aganwadi | 1 | 0.02 | 0.02 | 94% |
| Total | 422 | 4.32 | 3.88 |