| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 177 | 0.30 | 0.30 | 98% |
| 2 | Construction of Bund | 19 | 0.09 | 0.07 | 84% |
| 3 | Construction of Road and Culvert | 13 | 1.23 | 0.89 | 72% |
| 4 | Constr of Cement Concrete Roads | 11 | 0.10 | 0.09 | 89% |
| 5 | Land Development | 7 | 0.02 | 0.01 | 67% |
| 6 | Solid and Liquid Waste Management | 6 | 0.01 | 0.00 | 21% |
| 7 | Construction of Trench | 5 | 0.13 | 0.10 | 77% |
| 8 | Construction of Well | 5 | 0.14 | 0.11 | 82% |
| 9 | Construction of Crematorium | 4 | 0.07 | 0.07 | 96% |
| 10 | Construction of NADEP/Vermi Compost Pit | 3 | 0.00 | 0.00 | 92% |
| 11 | Repair & Maint of Community infrastructure | 3 | 0.21 | 0.14 | 71% |
| 12 | Construction of Play field | 2 | 0.04 | 0.02 | 60% |
| 13 | Constr of GP Bhawan | 2 | 0.13 | 0.10 | 79% |
| 14 | Plantation | 1 | 0.03 | 0.00 | 6% |
| 15 | Cattle Shed | 1 | 0.01 | 0.01 | 86% |
| 16 | Community Sanitary Complex | 1 | 0.01 | 0.01 | 100% |
| 17 | Construction of Percolation Tank | 1 | 0.03 | 0.02 | 80% |
| 18 | Constr of Aganwadi | 1 | 0.02 | 0.02 | 93% |
| 19 | Farm Pond | 1 | 0.00 | 0.00 | 81% |
| Total | 263 | 2.57 | 1.98 |