MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-09-01 08:48:19.512575
to
to
Reset filters
Scope
Works completed
213
Sanctioned (pure scheme)
₹1.36 Cr
Expenditure since inception
₹78.63 L

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Constr of Cement Concrete Roads
25 works
₹33.09 L sanctioned
₹20.06 L spent (61%)
02
Rural Housing
134 works
₹24.13 L sanctioned
₹23.85 L spent (99%)
03
Construction of Road and Culvert
5 works
₹19.53 L sanctioned
₹8.50 L spent (43%)
04
Land Development
10 works
₹12.21 L sanctioned
₹5.87 L spent (48%)
05
Construction of Tank
1 works
₹10.69 L sanctioned
₹1.08 L spent (10%)
06
Construction of Check Dam/Stop Dam
3 works
₹10.30 L sanctioned
₹5.47 L spent (53%)
07
Plantation
4 works
₹7.86 L sanctioned
₹3.13 L spent (40%)
08
Renovation of traditional water bodies
2 works
₹4.26 L sanctioned
₹1.76 L spent (41%)
09
Construction of Play field
1 works
₹3.62 L sanctioned
₹56,613 spent (16%)
10
Constr of Compound wall
3 works
₹2.93 L sanctioned
₹2.16 L spent (73%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 134 24.13 23.85
99%
2 Constr of Cement Concrete Roads 25 33.09 20.06
61%
3 Land Development 10 12.21 5.87
48%
4 Construction of Road and Culvert 5 19.53 8.50
44%
5 Construction of Recharge Pits 5 0.15 0.10
70%
6 Roof Water Harvesting on gov/panchayat bldg 5 0.27 0.24
90%
7 Goat Shelter 4 2.16 1.89
88%
8 Construction of Bund 4 1.30 0.87
67%
9 Plantation 4 7.86 3.13
40%
10 Construction of Check Dam/Stop Dam 3 10.30 5.47
53%
11 Constr of Compound wall 3 2.93 2.16
73%
12 Renovation of traditional water bodies 2 4.26 1.76
41%
13 Culvert 2 0.73 0.46
63%
14 Construction of NADEP/Vermi Compost Pit 2 0.34 0.23
69%
15 Construction of Play field 1 3.62 0.57
16%
16 Bio-Fertilizer 1 0.63 0.50
81%
17 Construction of Tank 1 10.69 1.08
10%
18 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.51 0.20
39%
19 Construction of Crematorium 1 1.80 1.69
94%
Total 213 136.50 78.63
All 19 rows (zero-value rows hidden) ⇩ Export to Excel