MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-09-16 08:34:45.218851
to
to
Reset filters
Scope
Works completed
351
Sanctioned (pure scheme)
₹3.99 Cr
Expenditure since inception
₹3.08 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Bund
51 works
₹1.04 Cr sanctioned
₹71.05 L spent (69%)
02
Construction of Check Dam/Stop Dam
44 works
₹75.69 L sanctioned
₹49.97 L spent (66%)
03
Construction of Road and Culvert
11 works
₹50.22 L sanctioned
₹43.79 L spent (87%)
04
Rural Housing
139 works
₹24.46 L sanctioned
₹23.98 L spent (98%)
05
Solid and Liquid Waste Management
3 works
₹24.09 L sanctioned
₹23.90 L spent (99%)
06
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
3 works
₹19.02 L sanctioned
₹11.32 L spent (60%)
07
Other Works
4 works
₹11.67 L sanctioned
₹10.68 L spent (92%)
08
Farm Pond
7 works
₹10.89 L sanctioned
₹7.51 L spent (69%)
09
Constr of Cement Concrete Roads
11 works
₹10.71 L sanctioned
₹10.09 L spent (94%)
10
Cattle Shed
19 works
₹8.74 L sanctioned
₹7.77 L spent (89%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 139 0.24 0.24
98%
2 Construction of Bund 51 1.04 0.71
69%
3 Construction of Check Dam/Stop Dam 44 0.76 0.50
66%
4 Land Development 24 0.08 0.07
90%
5 Cattle Shed 19 0.09 0.08
89%
6 Construction of NADEP/Vermi Compost Pit 14 0.01 0.01
92%
7 Construction of Road and Culvert 11 0.50 0.44
87%
8 Constr of Cement Concrete Roads 11 0.11 0.10
94%
9 Farm Pond 7 0.11 0.08
69%
10 Other Works 4 0.12 0.11
92%
11 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 3 0.19 0.11
60%
12 Plantation 3 0.09 0.05
55%
13 Construction of Crematorium 3 0.05 0.05
94%
14 Solid and Liquid Waste Management 3 0.24 0.24
99%
15 Construction of Well 3 0.06 0.06
96%
16 Construction of Tank 2 0.08 0.06
73%
17 Renovation of traditional water bodies 2 0.04 0.08
189%
18 Boulder Check/Gully Plug 1 0.01 0.01
87%
19 Community Sanitary Complex 1 0.01 0.00
43%
20 Constr of Compound wall 1 0.01 0.01
84%
21 Construction of Play field 1 0.02 0.01
83%
22 Construction of Recharge Pits 1 0.00 0.00
41%
23 Construction of Trench 1 0.03 0.02
49%
24 Culvert 1 0.03 0.03
93%
25 Repair & maint of Pond/ Tank 1 0.08 0.03
34%
Total 351 3.99 3.08
All 25 rows (zero-value rows hidden) ⇩ Export to Excel