Showcase — Completed Works

Rollup last refreshed: 2026-09-10 07:02:43.339169
to
to
Reset filters
Scope
Works completed
372
Sanctioned (pure scheme)
₹2.27 Cr
Expenditure since inception
₹1.56 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Rural Housing
273 works
₹48.58 L sanctioned
₹48.39 L spent (100%)
02
Construction of Road and Culvert
9 works
₹46.08 L sanctioned
₹21.72 L spent (47%)
03
Construction of Check Dam/Stop Dam
16 works
₹31.28 L sanctioned
₹19.16 L spent (61%)
04
Constr of Cement Concrete Roads
29 works
₹25.96 L sanctioned
₹18.94 L spent (73%)
05
Plantation
7 works
₹12.64 L sanctioned
₹30,773 spent (2%)
06
Constr of GP Bhawan
4 works
₹8.86 L sanctioned
₹8.86 L spent (100%)
07
Construction of Well
3 works
₹6.60 L sanctioned
₹3.57 L spent (54%)
08
Repair & maint of Pond/ Tank
1 works
₹5.59 L sanctioned
₹4.04 L spent (72%)
09
Construction of Crematorium
3 works
₹5.40 L sanctioned
₹5.34 L spent (99%)
10
Constr of Aganwadi
1 works
₹5.00 L sanctioned
₹4.99 L spent (100%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 273 48.58 48.39
100%
2 Constr of Cement Concrete Roads 29 25.96 18.94
73%
3 Construction of Check Dam/Stop Dam 16 31.28 19.16
61%
4 Land Development 9 4.80 3.26
68%
5 Construction of Road and Culvert 9 46.08 21.72
47%
6 Plantation 7 12.64 0.31
2%
7 Constr of GP Bhawan 4 8.86 8.86
100%
8 Construction of Recharge Pits 4 2.18 0.98
45%
9 Construction of Crematorium 3 5.40 5.34
99%
10 Construction of Well 3 6.60 3.57
54%
11 Farm Pond 2 4.80 2.50
52%
12 Goat Shelter 2 1.03 0.15
15%
13 Construction of NADEP/Vermi Compost Pit 2 4.95 4.71
95%
14 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.63 0.56
88%
15 Constr of Aganwadi 1 5.00 4.99
100%
16 Constr of Gabion 1 2.33 1.59
68%
17 Well Recharge 1 0.56 0.43
78%
18 Solid and Liquid Waste Management 1 1.20 1.18
98%
19 Construction of Percolation Tank 1 4.25 0.73
17%
20 Repair & maint of Pond/ Tank 1 5.59 4.04
72%
21 Construction of Toilets 1 1.00 1.00
100%
22 Constr of Compound wall 1 3.50 3.50
100%
Total 372 227.22 155.90
All 22 rows (zero-value rows hidden) ⇩ Export to Excel