MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
181
Sanctioned (pure scheme)
₹1.94 Cr
Expenditure since inception
₹1.62 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
14 works
₹75.45 L sanctioned
₹63.47 L spent (84%)
02
Constr of Cement Concrete Roads
24 works
₹29.54 L sanctioned
₹24.07 L spent (81%)
03
Construction of Check Dam/Stop Dam
3 works
₹21.71 L sanctioned
₹19.10 L spent (88%)
04
Rural Housing
67 works
₹14.07 L sanctioned
₹13.96 L spent (99%)
05
Construction of Tank
2 works
₹9.19 L sanctioned
₹7.66 L spent (83%)
06
Construction of Trench
3 works
₹7.97 L sanctioned
₹6.76 L spent (85%)
07
Plantation
3 works
₹6.93 L sanctioned
₹1.04 L spent (15%)
08
Terracing
1 works
₹5.18 L sanctioned
₹5.17 L spent (100%)
09
Land Development
2 works
₹4.79 L sanctioned
₹4.59 L spent (96%)
10
Constr of Aganwadi
2 works
₹3.90 L sanctioned
₹3.72 L spent (95%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 67 14.07 13.96
99%
2 Construction of Toilets 33 1.91 1.81
94%
3 Constr of Cement Concrete Roads 24 29.54 24.07
82%
4 Construction of Road and Culvert 14 75.45 63.47
84%
5 Construction of Recharge Pits 10 1.63 0.84
52%
6 Well Recharge 6 0.65 0.32
50%
7 Construction of Check Dam/Stop Dam 3 21.71 19.10
88%
8 Cattle Shed 3 2.12 1.96
92%
9 Construction of Trench 3 7.97 6.76
85%
10 Plantation 3 6.93 1.04
15%
11 Land Development 2 4.79 4.59
96%
12 Construction of Tank 2 9.19 7.66
83%
13 Solid and Liquid Waste Management 2 1.33 1.31
98%
14 Constr of Aganwadi 2 3.90 3.72
95%
15 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 1.97 1.70
87%
16 Farm Pond 1 0.56 0.44
79%
17 Construction of NADEP/Vermi Compost Pit 1 0.14 0.13
93%
18 Terracing 1 5.18 5.17
100%
19 Community Sanitary Complex 1 0.88 0.47
53%
20 Repair & maint of Pond/ Tank 1 2.67 2.61
98%
21 Construction of Bund 1 1.13 0.96
85%
Total 181 193.72 162.07
All 21 rows (zero-value rows hidden) ⇩ Export to Excel