MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
177
Sanctioned (pure scheme)
₹2.76 Cr
Expenditure since inception
₹2.02 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
8 works
₹86.50 L sanctioned
₹64.73 L spent (75%)
02
Farm Pond
22 works
₹64.60 L sanctioned
₹50.84 L spent (79%)
03
Constr of Cement Concrete Roads
42 works
₹27.32 L sanctioned
₹19.20 L spent (70%)
04
Construction of Well
9 works
₹16.17 L sanctioned
₹9.23 L spent (57%)
05
Underground Dyke for Ground Water Recharge
2 works
₹14.16 L sanctioned
₹12.75 L spent (90%)
06
Plantation
6 works
₹12.52 L sanctioned
₹3.81 L spent (30%)
07
Construction of Percolation Tank
2 works
₹12.40 L sanctioned
₹8.21 L spent (66%)
08
Land Development
9 works
₹8.28 L sanctioned
₹5.45 L spent (66%)
09
Rural Housing
41 works
₹7.65 L sanctioned
₹7.62 L spent (100%)
10
Construction of Check Dam/Stop Dam
3 works
₹7.58 L sanctioned
₹6.93 L spent (91%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Constr of Cement Concrete Roads 42 27.32 19.20
70%
2 Rural Housing 41 7.65 7.62
100%
3 Farm Pond 22 64.60 50.84
79%
4 Construction of NADEP/Vermi Compost Pit 14 1.88 1.52
81%
5 Land Development 9 8.28 5.45
66%
6 Construction of Well 9 16.17 9.23
57%
7 Construction of Road and Culvert 8 86.50 64.73
75%
8 Plantation 6 12.52 3.81
30%
9 Construction of Check Dam/Stop Dam 3 7.58 6.93
91%
10 Well Recharge 3 0.78 0.76
98%
11 Terracing 2 3.65 2.93
80%
12 Construction of Crematorium 2 3.60 3.44
96%
13 Construction of Percolation Tank 2 12.40 8.21
66%
14 Construction of Play field 2 2.12 0.00
0%
15 Underground Dyke for Ground Water Recharge 2 14.16 12.75
90%
16 Construction of Trench 1 0.26 0.25
95%
17 Constr of Aganwadi 1 1.80 1.47
82%
18 Constr of Gabion 1 1.97 1.55
79%
19 Construction of Recharge Pits 1 0.13 0.09
70%
20 Construction of Toilets 1 0.03 0.03
100%
21 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.99 0.82
83%
22 Nursery Development 1 0.15 0.10
69%
23 Renovation of traditional water bodies 1 0.40 0.24
59%
24 Repair & maint of Pond/ Tank 1 0.50 0.28
56%
25 Solid and Liquid Waste Management 1 0.37 0.13
34%
Total 177 275.79 202.38
All 25 rows (zero-value rows hidden) ⇩ Export to Excel