MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-09-06 07:04:10.165253
to
to
Reset filters
Scope
Works completed
506
Sanctioned (pure scheme)
₹5.46 Cr
Expenditure since inception
₹4.67 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
110 works
₹2.01 Cr sanctioned
₹2.47 Cr spent (123%)
02
Plantation
78 works
₹1.43 Cr sanctioned
₹66.46 L spent (46%)
03
Construction of Road and Culvert
7 works
₹66.23 L sanctioned
₹39.30 L spent (59%)
04
Rural Housing
219 works
₹43.90 L sanctioned
₹43.06 L spent (98%)
05
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
7 works
₹31.00 L sanctioned
₹25.60 L spent (83%)
06
Farm Pond
16 works
₹21.69 L sanctioned
₹14.28 L spent (66%)
07
Constr of Cement Concrete Roads
14 works
₹10.04 L sanctioned
₹8.88 L spent (88%)
08
Land Development
5 works
₹5.48 L sanctioned
₹4.09 L spent (75%)
09
Constr of Aganwadi
1 works
₹5.48 L sanctioned
₹1.72 L spent (31%)
10
Renovation of traditional water bodies
1 works
₹4.90 L sanctioned
₹44,191 spent (9%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 219 0.44 0.43
98%
2 Construction of Well 110 2.01 2.47
123%
3 Plantation 78 1.43 0.66
46%
4 Farm Pond 16 0.22 0.14
66%
5 Solid and Liquid Waste Management 15 0.02 0.02
87%
6 Construction of NADEP/Vermi Compost Pit 15 0.02 0.02
97%
7 Constr of Cement Concrete Roads 14 0.10 0.09
89%
8 Construction of Road and Culvert 7 0.66 0.39
59%
9 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 7 0.31 0.26
83%
10 Construction of Bund 6 0.01 0.00
42%
11 Land Development 5 0.05 0.04
75%
12 Construction of Toilets 3 0.00 0.00
101%
13 Constr of Kitchen Shed 2 0.00 0.00
88%
14 Repair & maint of Pond/ Tank 2 0.01 0.01
90%
15 Community Sanitary Complex 1 0.00 0.00
97%
16 Constr of Aganwadi 1 0.05 0.02
31%
17 Constr of Compound wall 1 0.00 0.00
100%
18 Construction of Check Dam/Stop Dam 1 0.03 0.07
240%
19 Construction of Crematorium 1 0.02 0.02
98%
20 Culvert 1 0.00 0.00
107%
21 Renovation of traditional water bodies 1 0.05 0.00
9%
Total 506 5.46 4.67
All 21 rows (zero-value rows hidden) ⇩ Export to Excel