| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 211 | 41.52 | 40.76 | 98% |
| 2 | Plantation | 23 | 38.57 | 8.93 | 23% |
| 3 | Construction of Well | 22 | 39.83 | 44.96 | 113% |
| 4 | Constr of Cement Concrete Roads | 9 | 17.18 | 7.80 | 45% |
| 5 | Construction of Road and Culvert | 9 | 71.42 | 78.74 | 110% |
| 6 | Other Works | 8 | 3.20 | 0.64 | 20% |
| 7 | Farm Pond | 6 | 17.82 | 13.42 | 75% |
| 8 | Construction of Bund | 4 | 1.57 | 1.20 | 77% |
| 9 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 3 | 22.68 | 19.89 | 88% |
| 10 | Repair & maint of Pond/ Tank | 3 | 1.14 | 0.99 | 87% |
| 11 | Cattle Shed | 2 | 2.20 | 0.15 | 7% |
| 12 | Construction of Crematorium | 2 | 3.60 | 3.45 | 96% |
| 13 | Culvert | 2 | 8.03 | 7.77 | 97% |
| 14 | Terracing | 2 | 9.81 | 8.44 | 86% |
| 15 | Construction of Check Dam/Stop Dam | 2 | 7.28 | 5.21 | 72% |
| 16 | Construction of Trench | 1 | 21.28 | 24.55 | 115% |
| 17 | Constr of Aganwadi | 1 | 1.80 | 0.78 | 43% |
| 18 | Construction of Percolation Tank | 1 | 8.91 | 4.71 | 53% |
| 19 | Construction of Play field | 1 | 2.44 | 1.13 | 46% |
| Total | 312 | 320.27 | 273.52 |