MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-08-08 07:29:29.870156
to
to
Reset filters
Scope
Works completed
312
Sanctioned (pure scheme)
₹3.68 Cr
Expenditure since inception
₹3.56 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
29 works
₹1.72 Cr sanctioned
₹1.93 Cr spent (112%)
02
Plantation
12 works
₹37.74 L sanctioned
₹11.62 L spent (31%)
03
Rural Housing
151 works
₹28.57 L sanctioned
₹27.73 L spent (97%)
04
Constr of Cement Concrete Roads
28 works
₹24.86 L sanctioned
₹48.45 L spent (195%)
05
Farm Pond
8 works
₹21.37 L sanctioned
₹13.65 L spent (64%)
06
Renovation of traditional water bodies
4 works
₹11.77 L sanctioned
₹9.16 L spent (78%)
07
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
4 works
₹11.72 L sanctioned
₹9.42 L spent (80%)
08
Construction of Percolation Tank
1 works
₹9.48 L sanctioned
₹4.71 L spent (50%)
09
Culvert
3 works
₹9.18 L sanctioned
₹1.60 L spent (17%)
10
Construction of Well
5 works
₹7.30 L sanctioned
₹4.42 L spent (60%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 151 0.29 0.28
97%
2 Construction of Toilets 32 0.04 0.04
92%
3 Construction of Road and Culvert 29 1.72 1.93
112%
4 Constr of Cement Concrete Roads 28 0.25 0.48
195%
5 Plantation 12 0.38 0.12
31%
6 Land Development 12 0.03 0.10
299%
7 Farm Pond 8 0.21 0.14
64%
8 Underground Dyke for Ground Water Recharge 6 0.02 0.02
81%
9 Construction of Trench 5 0.06 0.05
82%
10 Construction of Well 5 0.07 0.04
61%
11 Renovation of traditional water bodies 4 0.12 0.09
78%
12 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 4 0.12 0.09
80%
13 Culvert 3 0.09 0.02
17%
14 Construction of Crematorium 2 0.04 0.02
44%
15 Construction of Check Dam/Stop Dam 2 0.00 0.00
35%
16 Well Recharge 1 0.00 0.00
52%
17 Constr of Aganwadi 1 0.02 0.01
60%
18 Construction of Bund 1 0.00 0.00
32%
19 Construction of Percolation Tank 1 0.09 0.05
50%
20 Other Works 1 0.00 0.00
26%
21 Repair & maint of Pond/ Tank 1 0.05 0.02
42%
22 Terracing 1 0.02 0.02
88%
23 Boulder Check/Gully Plug 1 0.05 0.05
110%
24 Solid and Liquid Waste Management 1 0.00 0.00
97%
Total 312 3.68 3.56