Showcase — Completed Works

Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
361
Sanctioned (pure scheme)
₹3.29 Cr
Expenditure since inception
₹3.00 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Road and Culvert
15 works
₹66.79 L sanctioned
₹78.87 L spent (118%)
02
Construction of Well
36 works
₹46.19 L sanctioned
₹34.43 L spent (75%)
03
Rural Housing
216 works
₹40.80 L sanctioned
₹39.89 L spent (98%)
04
Plantation
13 works
₹39.65 L sanctioned
₹29.09 L spent (73%)
05
Farm Pond
13 works
₹38.59 L sanctioned
₹29.58 L spent (77%)
06
Constr of Cement Concrete Roads
13 works
₹20.39 L sanctioned
₹23.10 L spent (113%)
07
Land Development
21 works
₹15.50 L sanctioned
₹14.80 L spent (96%)
08
Construction of Tank
1 works
₹10.97 L sanctioned
₹9.57 L spent (87%)
09
Construction of Water Drain/Diversion Channel/Drainage/Field Channel
2 works
₹10.06 L sanctioned
₹9.28 L spent (92%)
10
Construction of Crematorium
1 works
₹9.01 L sanctioned
₹43,858 spent (5%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 216 40.80 39.89
98%
2 Construction of Well 36 46.19 34.43
75%
3 Land Development 21 15.50 14.80
96%
4 Construction of Road and Culvert 15 66.79 78.87
118%
5 Constr of Cement Concrete Roads 13 20.39 23.10
113%
6 Farm Pond 13 38.59 29.58
77%
7 Plantation 13 39.65 29.09
73%
8 Solid and Liquid Waste Management 10 0.93 0.81
88%
9 Underground Dyke for Ground Water Recharge 8 2.40 1.94
81%
10 Construction of Trench 4 6.82 5.08
75%
11 Culvert 2 6.12 6.52
107%
12 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 2 10.06 9.28
92%
13 Renovation of traditional water bodies 1 4.75 2.33
49%
14 Construction of Bund 1 0.30 0.09
29%
15 Construction of Check Dam/Stop Dam 1 4.93 8.81
179%
16 Construction of Crematorium 1 9.01 0.44
5%
17 Construction of Embankment 1 4.43 3.89
88%
18 Construction of NADEP/Vermi Compost Pit 1 0.03 0.02
65%
19 Construction of Play field 1 0.00 1.80
0%
20 Construction of Tank 1 10.97 9.57
87%
Total 361 328.67 300.32