Showcase — Completed Works

Rollup last refreshed: 2026-09-16 08:34:45.218851
to
to
Reset filters
Scope
Works completed
447
Sanctioned (pure scheme)
₹11.73 Cr
Expenditure since inception
₹7.09 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
40 works
₹5.59 Cr sanctioned
₹1.73 Cr spent (31%)
02
Construction of Trench
60 works
₹1.47 Cr sanctioned
₹1.41 Cr spent (96%)
03
Underground Dyke for Ground Water Recharge
11 works
₹1.25 Cr sanctioned
₹1.21 Cr spent (97%)
04
Construction of Road and Culvert
13 works
₹86.33 L sanctioned
₹75.19 L spent (87%)
05
Construction of Bund
3 works
₹50.08 L sanctioned
₹30.11 L spent (60%)
06
Rural Housing
245 works
₹44.57 L sanctioned
₹38.48 L spent (86%)
07
Farm Pond
19 works
₹35.80 L sanctioned
₹34.40 L spent (96%)
08
Plantation
20 works
₹30.47 L sanctioned
₹11.79 L spent (39%)
09
Constr of Cement Concrete Roads
6 works
₹28.18 L sanctioned
₹23.29 L spent (83%)
10
Construction of Well
9 works
₹20.99 L sanctioned
₹19.63 L spent (94%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 245 0.45 0.38
86%
2 Construction of Trench 60 1.47 1.41
96%
3 Construction of Check Dam/Stop Dam 40 5.59 1.73
31%
4 Plantation 20 0.30 0.12
39%
5 Farm Pond 19 0.36 0.34
96%
6 Construction of Road and Culvert 13 0.86 0.75
87%
7 Underground Dyke for Ground Water Recharge 11 1.25 1.21
97%
8 Construction of Well 9 0.21 0.20
94%
9 Constr of Cement Concrete Roads 6 0.28 0.23
83%
10 Repair & maint of Water Harvesting Structures 6 0.05 0.04
82%
11 Construction of Bund 3 0.50 0.30
60%
12 Repair & Maint of Community infrastructure 2 0.04 0.04
100%
13 Land Development 2 0.02 0.01
68%
14 Goat Shelter 2 0.01 0.00
14%
15 Construction of NADEP/Vermi Compost Pit 1 0.00 0.00
86%
16 Repair & maint of Road 1 0.15 0.14
97%
17 Construction of Percolation Tank 1 0.05 0.05
92%
18 Terracing 1 0.00 0.00
17%
19 Boulder Check/Gully Plug 1 0.02 0.01
55%
20 Construction of Toilets 1 0.00 0.00
96%
21 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.09 0.09
96%
22 Construction of Crematorium 1 0.02 0.02
99%
23 Renovation of traditional water bodies 1 0.01 0.01
95%
Total 447 11.73 7.09
All 23 rows (zero-value rows hidden) ⇩ Export to Excel