Works completed
295
Sanctioned (pure scheme)
₹4.17 Cr
Expenditure since inception
₹3.35 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Well
31 works
₹88.31 L sanctioned
₹75.79 L spent (86%)
02
Construction of Road and Culvert
7 works
₹80.52 L sanctioned
₹79.76 L spent (99%)
03
Rural Housing
170 works
₹31.13 L sanctioned
₹29.82 L spent (96%)
04
Cattle Shed
1 works
₹27.72 L sanctioned
₹26.87 L spent (97%)
05
Construction of Check Dam/Stop Dam
6 works
₹27.50 L sanctioned
₹25.21 L spent (92%)
06
Farm Pond
12 works
₹24.55 L sanctioned
₹19.38 L spent (79%)
07
Plantation
8 works
₹18.87 L sanctioned
₹1.94 L spent (10%)
08
Construction of Percolation Tank
4 works
₹16.44 L sanctioned
₹7.13 L spent (43%)
09
Grass Land Development
1 works
₹15.29 L sanctioned
₹5.84 L spent (38%)
10
Land Development
4 works
₹13.80 L sanctioned
₹11.99 L spent (87%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 170 31.13 29.82
96%
2 Construction of Well 31 88.31 75.79
86%
3 Constr of Cement Concrete Roads 16 12.58 11.98
95%
4 Farm Pond 12 24.55 19.38
79%
5 Solid and Liquid Waste Management 10 6.71 6.12
91%
6 Plantation 8 18.87 1.94
10%
7 Construction of Road and Culvert 7 80.52 79.76
99%
8 Construction of Check Dam/Stop Dam 6 27.50 25.21
92%
9 Construction of Trench 4 4.90 1.75
36%
10 Land Development 4 13.80 11.99
87%
11 Construction of Percolation Tank 4 16.44 7.13
43%
12 Construction of Bund 3 1.27 1.02
81%
13 Construction of building/workshed for SHG 3 3.00 2.96
99%
14 Construction of NADEP/Vermi Compost Pit 3 1.71 1.60
94%
15 Construction of Toilets 2 6.00 5.73
96%
16 Well Recharge 1 0.26 0.10
37%
17 Community Sanitary Complex 1 0.44 0.44
99%
18 Constr of GP Bhawan 1 13.63 5.44
40%
19 Constr of Kitchen Shed 1 0.27 0.25
92%
20 Construction of Crematorium 1 2.00 1.96
98%
21 Construction of Play field 1 3.53 3.36
95%
22 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 3.45 3.29
95%
23 Culvert 1 1.50 0.75
50%
24 Grass Land Development 1 15.29 5.84
38%
25 Repair & maint of Pond/ Tank 1 9.63 4.51
47%
26 Cattle Shed 1 27.72 26.87
97%
27 Underground Dyke for Ground Water Recharge 1 2.14 0.22
10%
Total 295 417.15 335.21
All 27 rows (zero-value rows hidden) ⇩ Export to Excel