Showcase — Completed Works
Rollup last refreshed: 2026-07-11 02:05:34.314168
Top new work types
Top 10 · ranked by sanction cost (Admin Config)
01
Cattle Shed
5 works
₹41.57 L sanctioned
₹40.92 L spent (98%)
02
Plantation
8 works
₹26.67 L sanctioned
₹7.51 L spent (28%)
03
Rural Housing
82 works
₹16.39 L sanctioned
₹15.97 L spent (97%)
04
Constr of Cement Concrete Roads
20 works
₹8.72 L sanctioned
₹7.56 L spent (87%)
05
Land Development
10 works
₹7.11 L sanctioned
₹3.21 L spent (45%)
06
Construction of Percolation Tank
1 works
₹7.00 L sanctioned
₹860 spent (0%)
07
Construction of Road and Culvert
1 works
₹4.73 L sanctioned
₹14,340 spent (3%)
08
Solid and Liquid Waste Management
11 works
₹4.58 L sanctioned
₹3.85 L spent (84%)
09
Construction of Crematorium
1 works
₹1.80 L sanctioned
₹1.67 L spent (93%)
10
Construction of Bund
2 works
₹1.67 L sanctioned
₹1.15 L spent (68%)