MGNREGA Works Dashboard
MGNREGA VBGRAMG MGNREGA + VBGRAMG
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-09-01 08:48:19.512575
to
to
Reset filters
Scope
Works completed
258
Sanctioned (pure scheme)
₹1.92 Cr
Expenditure since inception
₹99.83 L

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Plantation
23 works
₹51.47 L sanctioned
₹14.75 L spent (29%)
02
Construction of Road and Culvert
5 works
₹43.87 L sanctioned
₹9.65 L spent (22%)
03
Constr of Cement Concrete Roads
25 works
₹17.45 L sanctioned
₹15.39 L spent (88%)
04
Construction of Check Dam/Stop Dam
12 works
₹15.39 L sanctioned
₹10.36 L spent (67%)
05
Land Development
26 works
₹13.89 L sanctioned
₹9.53 L spent (69%)
06
Rural Housing
71 works
₹11.59 L sanctioned
₹11.03 L spent (95%)
07
Construction of Well
3 works
₹5.61 L sanctioned
₹4.48 L spent (80%)
08
Constr of GP Bhawan
2 works
₹5.04 L sanctioned
₹4.29 L spent (85%)
09
Constr of Aganwadi
1 works
₹4.49 L sanctioned
₹3.57 L spent (80%)
10
Cattle Shed
5 works
₹4.40 L sanctioned
₹4.03 L spent (92%)

Detailed breakdown (All amounts in ₹ Lakh)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 71 11.59 11.03
95%
2 Construction of Toilets 41 1.30 1.30
100%
3 Land Development 26 13.89 9.53
69%
4 Constr of Cement Concrete Roads 25 17.45 15.39
88%
5 Plantation 23 51.47 14.75
29%
6 Construction of Trench 20 0.54 0.51
94%
7 Construction of Check Dam/Stop Dam 12 15.39 10.36
67%
8 Construction of NADEP/Vermi Compost Pit 6 1.71 1.73
101%
9 Cattle Shed 5 4.40 4.03
92%
10 Construction of Bund 5 3.37 1.55
46%
11 Construction of Road and Culvert 5 43.87 9.65
22%
12 Solid and Liquid Waste Management 4 2.42 1.67
69%
13 Construction of Well 3 5.61 4.48
80%
14 Construction of Play field 2 3.67 0.92
25%
15 Constr of GP Bhawan 2 5.04 4.29
85%
16 Roof Water Harvesting on gov/panchayat bldg 2 0.97 0.84
87%
17 Repair & Maint of Bund 1 0.51 0.42
83%
18 Terracing 1 0.61 0.41
67%
19 Constr of Aganwadi 1 4.49 3.57
80%
20 Construction of Crematorium 1 1.83 1.76
96%
21 Construction of Percolation Tank 1 1.61 1.30
81%
22 Community Sanitary Complex 1 0.30 0.32
107%
Total 258 192.01 99.83