| Sr. | New Work Type | Completed | Sanctioned | Expenditure | Exp. % |
|---|---|---|---|---|---|
| 1 | Rural Housing | 96 | 16.56 | 16.40 | 99% |
| 2 | Constr of Cement Concrete Roads | 16 | 9.42 | 7.87 | 84% |
| 3 | Land Development | 12 | 12.35 | 6.95 | 56% |
| 4 | Construction of Toilets | 7 | 0.80 | 0.41 | 52% |
| 5 | Construction of Road and Culvert | 7 | 40.80 | 23.42 | 57% |
| 6 | Construction of Trench | 6 | 7.88 | 4.52 | 57% |
| 7 | Construction of Bund | 5 | 3.44 | 2.82 | 82% |
| 8 | Construction of Well | 4 | 3.89 | 3.57 | 92% |
| 9 | Plantation | 4 | 21.39 | 1.23 | 6% |
| 10 | Cattle Shed | 3 | 4.04 | 2.46 | 61% |
| 11 | Solid and Liquid Waste Management | 2 | 0.61 | 0.19 | 31% |
| 12 | Works for Flood Control and Protection | 2 | 1.10 | 1.09 | 99% |
| 13 | Construction of Water Drain/Diversion Channel/Drainage/Field Channel | 2 | 2.64 | 1.95 | 74% |
| 14 | Farm Pond | 2 | 2.31 | 1.19 | 52% |
| 15 | Constr of GP Bhawan | 2 | 5.29 | 4.55 | 86% |
| 16 | Construction of Tank | 2 | 3.89 | 2.88 | 74% |
| 17 | Constr of Compound wall | 1 | 0.16 | 0.16 | 103% |
| 18 | Terracing | 1 | 1.92 | 1.49 | 78% |
| 19 | Well Recharge | 1 | 0.41 | 0.31 | 76% |
| 20 | Community Sanitary Complex | 1 | 0.45 | 0.38 | 84% |
| 21 | Construction of Play field | 1 | 1.87 | 0.95 | 51% |
| 22 | Construction of Check Dam/Stop Dam | 1 | 2.12 | 2.38 | 112% |
| Total | 178 | 143.33 | 87.18 |