Rollup last refreshed: 2026-07-11 02:05:34.314168
to
to
Reset filters
Scope
Works completed
620
Sanctioned (pure scheme)
₹4.58 Cr
Expenditure since inception
₹4.55 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Trench
22 works
₹1.06 Cr sanctioned
₹1.04 Cr spent (98%)
02
Construction of Check Dam/Stop Dam
10 works
₹69.89 L sanctioned
₹65.83 L spent (94%)
03
Rural Housing
391 works
₹67.79 L sanctioned
₹68.06 L spent (100%)
04
Plantation
18 works
₹48.74 L sanctioned
₹10.02 L spent (21%)
05
Construction of Road and Culvert
18 works
₹40.62 L sanctioned
₹72.13 L spent (178%)
06
Farm Pond
40 works
₹35.98 L sanctioned
₹27.17 L spent (76%)
07
Construction of Bund
26 works
₹18.19 L sanctioned
₹22.15 L spent (122%)
08
Land Development
43 works
₹15.82 L sanctioned
₹39.91 L spent (252%)
09
Repair & maint of Pond/ Tank
2 works
₹11.76 L sanctioned
₹10.38 L spent (88%)
10
Strengthening of Embankment
2 works
₹8.04 L sanctioned
₹6.52 L spent (81%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 391 0.68 0.68
100%
2 Land Development 43 0.16 0.40
252%
3 Farm Pond 40 0.36 0.27
76%
4 Construction of Bund 26 0.18 0.22
122%
5 Construction of Trench 22 1.06 1.04
98%
6 Plantation 18 0.49 0.10
21%
7 Construction of Road and Culvert 18 0.41 0.72
178%
8 Solid and Liquid Waste Management 14 0.05 0.04
83%
9 Construction of Check Dam/Stop Dam 10 0.70 0.66
94%
10 Construction of Recharge Pits 7 0.01 0.01
97%
11 Constr of Cement Concrete Roads 7 0.06 0.06
115%
12 Terracing 5 0.02 0.01
54%
13 Constr of Compound wall 5 0.02 0.02
95%
14 Construction of NADEP/Vermi Compost Pit 2 0.07 0.03
43%
15 Repair & maint of Pond/ Tank 2 0.12 0.10
88%
16 Roof Water Harvesting on gov/panchayat bldg 2 0.00 0.00
79%
17 Strengthening of Embankment 2 0.08 0.07
81%
18 Works for Flood Control and Protection 1 0.03 0.02
93%
19 Construction of Percolation Tank 1 0.04 0.03
97%
20 Construction of Toilets 1 0.00 0.00
99%
21 Construction of Well 1 0.02 0.02
91%
22 Culvert 1 0.00 0.00
98%
23 Boulder Check/Gully Plug 1 0.04 0.04
92%
Total 620 4.58 4.55
All 23 rows (zero-value rows hidden) ⇩ Export to Excel