Showcase — Completed Works

Rollup last refreshed: 2026-08-12 08:29:25.302981
to
to
Reset filters
Scope
Works completed
1,220
Sanctioned (pure scheme)
₹8.65 Cr
Expenditure since inception
₹6.46 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Construction of Check Dam/Stop Dam
105 works
₹1.82 Cr sanctioned
₹1.38 Cr spent (76%)
02
Construction of Bund
134 works
₹1.53 Cr sanctioned
₹1.21 Cr spent (79%)
03
Construction of Road and Culvert
13 works
₹1.34 Cr sanctioned
₹94.53 L spent (70%)
04
Rural Housing
473 works
₹93.43 L sanctioned
₹87.46 L spent (94%)
05
Plantation
29 works
₹72.92 L sanctioned
₹24.97 L spent (34%)
06
Other Works
11 works
₹44.86 L sanctioned
₹33.96 L spent (76%)
07
Land Development
64 works
₹43.98 L sanctioned
₹33.73 L spent (77%)
08
Farm Pond
268 works
₹41.34 L sanctioned
₹37.50 L spent (91%)
09
Repair & maint of Pond/ Tank
6 works
₹18.01 L sanctioned
₹11.58 L spent (64%)
10
Construction of Tank
1 works
₹16.34 L sanctioned
₹16.05 L spent (98%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 473 0.93 0.87
94%
2 Farm Pond 268 0.41 0.37
91%
3 Construction of Bund 134 1.53 1.21
79%
4 Construction of Check Dam/Stop Dam 105 1.82 1.38
76%
5 Construction of NADEP/Vermi Compost Pit 79 0.08 0.04
48%
6 Land Development 64 0.44 0.34
77%
7 Plantation 29 0.73 0.25
34%
8 Construction of Road and Culvert 13 1.34 0.95
70%
9 Other Works 11 0.45 0.34
76%
10 Boulder Check/Gully Plug 10 0.11 0.11
96%
11 Constr of Cement Concrete Roads 9 0.08 0.06
79%
12 Repair & maint of Pond/ Tank 6 0.18 0.12
64%
13 Well Recharge 3 0.15 0.11
75%
14 Solid and Liquid Waste Management 3 0.00 0.00
80%
15 Construction of Toilets 2 0.00 0.00
52%
16 Construction of Play field 2 0.02 0.00
5%
17 Construction of Embankment 2 0.06 0.04
61%
18 Renovation of traditional water bodies 2 0.02 0.01
49%
19 Construction of Percolation Tank 1 0.07 0.07
91%
20 Construction of Trench 1 0.03 0.02
80%
21 Construction of Well 1 0.02 0.02
74%
22 Construction of Tank 1 0.16 0.16
98%
23 Community Sanitary Complex 1 0.00 0.00
76%
Total 1,220 8.65 6.46
All 23 rows (zero-value rows hidden) ⇩ Export to Excel