MGNREGA Works Dashboard
Admin login

Showcase — Completed Works

Rollup last refreshed: 2026-08-11 08:31:20.212157
to
to
Reset filters
Scope
Works completed
1,159
Sanctioned (pure scheme)
₹8.77 Cr
Expenditure since inception
₹6.89 Cr

Top new work types

Top 10 · ranked by sanction cost (Admin Config)
01
Boulder Check/Gully Plug
117 works
₹1.47 Cr sanctioned
₹1.19 Cr spent (81%)
02
Construction of Bund
80 works
₹1.21 Cr sanctioned
₹93.75 L spent (78%)
03
Farm Pond
313 works
₹99.09 L sanctioned
₹73.85 L spent (75%)
04
Construction of Road and Culvert
21 works
₹72.38 L sanctioned
₹48.93 L spent (68%)
05
Land Development
74 works
₹71.35 L sanctioned
₹65.84 L spent (92%)
06
Rural Housing
367 works
₹69.49 L sanctioned
₹64.97 L spent (93%)
07
Plantation
28 works
₹66.26 L sanctioned
₹18.02 L spent (27%)
08
Constr of Cement Concrete Roads
16 works
₹57.52 L sanctioned
₹44.18 L spent (77%)
09
Construction of Check Dam/Stop Dam
60 works
₹38.86 L sanctioned
₹52.67 L spent (136%)
10
Well Recharge
10 works
₹34.43 L sanctioned
₹26.68 L spent (77%)

Detailed breakdown (All amounts in ₹ Crore)

By District / Block / Panchayat By New Work Type
Sr. New Work Type Completed Sanctioned Expenditure Exp. %
1 Rural Housing 367 0.69 0.65
94%
2 Farm Pond 313 0.99 0.74
75%
3 Boulder Check/Gully Plug 117 1.47 1.19
81%
4 Construction of Bund 80 1.21 0.94
78%
5 Land Development 74 0.71 0.66
92%
6 Construction of Check Dam/Stop Dam 60 0.39 0.53
136%
7 Plantation 28 0.66 0.18
27%
8 Construction of Road and Culvert 21 0.72 0.49
68%
9 Construction of Well 17 0.30 0.24
81%
10 Constr of Cement Concrete Roads 16 0.58 0.44
77%
11 Construction of Toilets 14 0.01 0.00
35%
12 Construction of NADEP/Vermi Compost Pit 11 0.01 0.01
57%
13 Well Recharge 10 0.34 0.27
78%
14 Repair & maint of Water Harvesting Structures 9 0.16 0.15
93%
15 Construction of Trench 8 0.04 0.03
84%
16 Community Sanitary Complex 2 0.01 0.01
95%
17 Repair & maint of Pond/ Tank 2 0.07 0.06
81%
18 Cattle Shed 2 0.01 0.01
82%
19 Constr of GP Bhawan 1 0.13 0.09
66%
20 Construction of Water Drain/Diversion Channel/Drainage/Field Channel 1 0.00 0.00
50%
21 Construction of Play field 1 0.05 0.04
84%
22 Constr of Gabion 1 0.01 0.01
72%
23 Construction of Spur 1 0.13 0.12
87%
24 Construction of Embankment 1 0.02 0.02
85%
25 Construction of Crematorium 1 0.02 0.01
79%
26 Repair & maint of Road 1 0.00 0.00
101%
Total 1,159 8.77 6.89
All 26 rows (zero-value rows hidden) ⇩ Export to Excel